China , the world's first AP1000, was commissioned in 2018. Four AP1000 reactors have been constructed in China, two at
Sanmen Nuclear Power Plant in
Zhejiang, and two at
Haiyang Nuclear Power Plant in
Shandong. The Sanmen 1 & 2 AP1000s were connected to the grid on July 2, 2018, and August 24, 2018, respectively. Haiyang 1 started commercial operation on October 22, 2018, and Haiyang 2 on January 9, 2019. In 2014,
China First Heavy Industries manufactured the first domestically produced AP1000 reactor pressure vessel, for the second AP1000 unit of
Sanmen Nuclear Power Station. The first four AP1000s to be built are to an earlier revision of the design without a strengthened containment structure to provide improved protection against an aircraft crash. China had officially adopted the AP1000 as a standard for inland nuclear projects. Following Westinghouse's bankruptcy in 2017, China decided in 2019 to build the domestically designed
Hualong One rather than the AP1000 at
Zhangzhou. After 2019, all plans for future AP1000 units were superseded by
CAP1000 units, which are a local standardization of the AP1000 design, transitional to the
CAP1400. It is said to have reduced cost and improved operation and maintenance attributes. As of 2021, site preparations have been done for
Haiyang,
Lufeng,
Sanmen, and
Xudabao for the construction of eight additional CAP1000 units. However, most of these projects are at a standstill, as construction of all CAP-1000 units has been slowed down significantly. Construction of the first CAP1000 unit at
Guangxi Bailong Nuclear Power Project began in January 2026. At the
Xudabao site, construction of two
VVER-1200 units for Xudabao 3 & 4 was started in 2021 while the planned CAP1000 units for phases 1 & 2 are still on hold.
Turkey In October 2015 it was announced that technology for the
İğneada Nuclear Power Plant in Turkey will come from US based firm
Westinghouse Electric Company in the form of two AP1000 and two Chinese
CAP1400. In 2016, the Minister of Energy and Natural Resources of the Republic of
Turkey,
Berat Albayrak, inspected the AP 1000 Shangdong Haiyang Nuclear Power Plant, which belongs to the China National State Nuclear Technology Corporation (
SNPTC), a subsidiary of the
China State Electricity Investment Corporation (SPIC).
United States Two reactors have been brought online at the
Vogtle Electric Generating Plant in the state of
Georgia (Units 3 & 4). In
South Carolina, two units were being constructed at the
Virgil C. Summer Nuclear Generating Station (Units 2 & 3). The project was abandoned in July 2017, 4 years after it began, due to Westinghouse's recent bankruptcy, major cost overruns, significant delays, and other issues. The project's primary shareholder (
SCANA) initially favored a plan to abandon development of Unit 3, while completing Unit 2. The plan was dependent on approval of a minority shareholder (
Santee Cooper). Santee Cooper's board voted to cease all construction resulting in termination of the entire project. All four reactors were identical and the two projects ran in parallel, with the first two reactors (Vogtle 3 and Summer 2) planned to be commissioned in 2019 and the remaining two (Vogtle 4 and Summer 3) in 2020. After Westinghouse filed for bankruptcy protection on March 29, 2017, the construction has stalled. On April 9, 2008,
Georgia Power Company reached a contract agreement with Westinghouse and Shaw for two AP1000 reactors to be built at Vogtle. The contract represents the first agreement for new nuclear development since the
Three Mile Island accident in 1979. The license request for the Vogtle site is based on revision 18 of the AP1000 design. On February 16, 2010, President Obama announced $8.33 billion in federal loan guarantees to construct the two AP1000 units at the Vogtle plant. The cost of building the two reactors was projected to be $14 billion, but has since increased to $30B with only one reactor online and the second remaining under construction. Georgia Power, which owns 45.7% of Vogtle, delayed the projected in-service dates to the fourth quarter of 2023, or first quarter of 2024, for Unit 4. Environmental groups opposed to the licensing of the two new AP1000 reactors to be built at Vogtle filed a new petition in April 2011 asking the Nuclear Regulatory Commission's commission to suspend the licensing process until more is known about the evolving
Fukushima I nuclear accidents. In February 2012, nine environmental groups filed a collective challenge to the certification of the Vogtle reactor design and in March they filed a challenge to the Vogtle license. In May 2013, the U.S. Court of Appeals ruled in favor of the Nuclear Regulatory Commission (NRC). In February 2012, the
US Nuclear Regulatory Commission approved the two proposed reactors at the Vogtle plant. For VC Summer, a delay of at least one year and extra costs of $1.2 billion were announced in October 2014, largely due to fabrication delays. Unit 2 was then expected to be substantially complete in late 2018 or early 2019, with unit 3 about a year later. In October 2013, US energy secretary
Ernest Moniz announced that China was to supply components to the US nuclear power plants under construction as part of a bilateral co-operation agreement between the two countries. Since China's
State Nuclear Power Technology Corporation (SNPTC) acquired Westinghouse's AP1000 technology in 2006, it has developed a manufacturing supply chain capable of supplying international power projects. Industry analysts have highlighted a number of problems facing China's expansion in the nuclear market including continued gaps in their supply chain, coupled with Western fears of political interference and Chinese inexperience in the economics of nuclear power. On July 31, 2017, after an extensive review into the costs of constructing Units 2 and 3, South Carolina Electric and Gas decided to stop construction of the reactors at VC Summer and will file a Petition for Approval of Abandonment with the Public Service Commission of South Carolina. On October 14, 2022, Georgia Power announced that loading of nuclear fuel at Vogtle Unit 3 had begun. On April 1, 2023, Georgia Power announced that Vogtle Unit 3 had made a connection to the grid and began supplying electricity for the first time, and on May 29, Unit 3 reached its maximum designed power output. Hot functional testing on Vogtle Unit 4 was completed on May 1, 2023. It went into commercial operation in March 2024. In 2025, Fermi America signed an agreement with Doosan Enerbility, a South Korean nuclear equipment firm to deploy four Westinghouse AP1000 nuclear reactors as part of its data center development in Amarillo, Texas.
Ukraine On August 31, 2021, the head of SE NNEGC Energoatom Petro Kotin and the President and chief executive officer of Westinghouse Patrick Fragman signed a memorandum of cooperation for building Westinghouse AP1000 reactors in Ukraine. The contract was signed on November 22, 2021. The memorandum and contract between the two companies concerns the completion of unit 4 of the
Khmelnytskyi Nuclear Power Plant with the AP1000 as well as four more power units of other nuclear power plants in Ukraine.
Poland Poland plans to build three AP1000 reactors in
Choczewo near the Baltic Sea, the site is called
Lubiatowo-Kopalino. The total investment costs of the project are estimated to be about EUR 42 billion (USD 47 billion as of end of 2025).
Bulgaria Bulgaria plans to build two AP1000 reactors in
Kozloduy Nuclear Power Plant.
Slovakia Slovakia plans to build a single AP1000 unit at the
Bohunice Nuclear Power Plant as a replacement for the decommissioned
VVER440 (230 type) units at the V1 plant. == Failed bid or ventures ==