1970–2000 •
1974: The nuclear submarine project was sanctioned following the
Smiling Buddha tests under the then
Prime Minister,
Indira Gandhi. •
12 February 2009: The Advanced Technology Vessel project, meant to deliver three submarines, is part of a $2.9 billion programme to build five nuclear submarines. As per the then
Defence Minister,
A. K. Antony, the first submarine was in the final stages of construction after
supply chain bottlenecks were cleared and DRDO was already developing
submarine-launched ballistic missile. The project was conceived in 1970s and operationalised in 1980s, though public acknowledgement never came from official sources until this announcement by the defence minister. There were delays to miniaturise the
nuclear reactor core for the submarine and Russian technology help was sought to solve the issues without delays. Another factor that resulted in delays was lack of
metallurgical expertise and lack of experience of Indian hull makers on the chosen material for the submarine. The successful development of a nuclear submarine came after two failed attempts in the 1970s and 1980s. •
16 July 2009: Multiple reports suggested that the first vessel under the Advanced Technology Vessel would be launched by
Gursharan Kaur, the wife of the then Prime Minister,
Manmohan Singh, on 26 July 2009. The ceremony would be held in
Naval Dockyard (Visakhapatnam). The vessel was named ''
, meaning "destroyer of enemies". The design is based on Charlie-I submarines, while both the displacement and submerged speed are higher than the Charlie-I designs. While being launched, the dry dock in the Shipbuilding Centre in Visakhapatnam will be flooded and the submarine would be moved out of the SBC. The vessel would be then towed to a nearby pier for harbour trials during which, the nuclear power plant and auxiliary systems would be validated before its sea trials in the Bay of Bengal. The submarine was expected to be commissioned within two to three years. Meanwhile, hull sections of two additional ATVs have been completed in the Hazira facility of Larsen & Toubro and are to be transported to the SBC soon after Arihant'' exits the dock space. Meanwhile, many expected that the operationalisation of the submarine would take much longer than two years. Harbour acceptance trials and followed by sea acceptance trials, including the surface and sub-surface domains, respectively, were to be conducted before commissioning the submarine. The submarine, equipped with
Sagarika missiles, •
13 December 2014: Arihant was entered sea for the first time after being flagged off for extensive sea trials following harbour trials. The sea acceptance trials for the submarine was initially slated for February 2012. •
25 November 2015: A dummy or unarmed B-05
Sagarika missile was successfully test fired from INS
Arihant from a depth of 20 metres. •
31 March 2016: The
K-4 missile was successfully tested from INS
Arihant, 45 nautical miles away from the
Vishakhapatnam coast. The missile with a dummy payload was launched from the submarine in full operational configuration. The trial was carried out with the support of the personnel of
Strategic Forces Command (SFC) while the
DRDO provided all the logistics. •
August 2016: The first boat of the class, INS
Arihant, was commissioned. •
19 November 2017: The second submarine, christened , was launched by the then defence minister,
Nirmala Sitharaman, with a low-profile, traditional ceremony. The vessel was floated out after flooding the drydock. Reportedly, commissioning of the vessel would take three years. It has an indigenous content of 60%. The third (S4) and fourth (S4*) submarine, with eight launcher units, was expected to be launched in 2020 and 2022, respectively. •
11–12 August 2018: The B-05 missile system was fired twice on 11th and once on 12th of August from INS
Arihant and was operationalised two decades since the missile systems development commenced. All the missiles followed the designated trajectories and were fired 10 km away from Visakhapatnam from a depth of 20 m. •
4 November 2018: Arihant completed its first deterrence patrol for 20 days. •
2022: Aridhaman begun sea trials. •
11 August 2024:
Arighaat was being prepared for being commissioned within two months
. •
29 August 2024:
Arighaat was commissioned in the presence of the
Defence Minister,
Rajnath Singh. •
16 October 2024: The fourth and final submarine of the class, with an indigenous content of 75% and equipped with K4 missiles, was launched. •
2 December 2025: Aridhaman had entered the final stages of trials and was expected to be commissioned soon. •
30 December 2025: The fourth submarine, S4*, had reportedly departed the harbour for sea trials a week earlier and is expected to be commissioned in early 2027. Meanwhile,
Aridhaman, the third unit had completed its sea trials a few weeks ago and is now to be commissioned in early 2026 after being delivered. •
5 January 2026: A report suggested that the final submarine, so far referred to as S4*, will be named INS
Arisudan. The name has been proposed by the ship-naming committee of the Indian Navy. The name is yet to be receive clearance by the defence ministry and eventually, the
President of India, who is also the Supreme Commander of the Armed Forces. •
3 April 2026: INS
Aridhaman was commissioned. ==Ships in class==