Background and the
Bristen peak from the north portal. The historic routes on the Gotthard (road and railway) follow the Reuss upwards, which flows west of the Bristen. Since the 13th century, the Gotthard Pass has been an important trade route from northern to southern Europe. Control of its access routes led to the birth of the
Swiss Confederacy. The Gotthard Pass is located halfway between
Lake Lucerne and
Lake Maggiore. It is the shortest link between the navigable
Rhine and the
Po. Before modern transport, the traverse of the pass took days, and snow makes it a challenge in winter. Quite late, compared to other current top-importance routes through the Alps (e.g.
Simplon,
San Bernardino,
Brenner,
Mont Cenis), namely in 1830, the first Saint-Gotthard Pass road was established after centuries-long usage of a
bridle path. From 1842 onwards, a daily course by the
Gotthard Post, a stagecoach drawn by five horses with ten seats, still took about 23 hours from
Como to
Flüelen. It would last until 1921. In 1882, with the inauguration of the
Gotthard Railway Tunnel, the travel time between
Altdorf and
Biasca was reduced dramatically to only hours, though often accompanied with overnight stays in large
Fin de siècle-hotels, for example in Biasca. In those days, it was still an adventure and it was only affordable to the rich. Electrification of the railway line in 1922 significantly reduced travel time again. Refilling water boilers of steam locomotives was no longer necessary. There were also the technical advantages of electrical engines and future technical improvements. From 1924, car transport on trains through the railway tunnel began. The road between
Göschenen and
Airolo over the summit of the pass, comporting notably the
Schöllenen ravine and the
Tremola, had countless hairpin turns and serpentine curves, dropping in altitude. It posed a huge challenge for automobiles of those days. From 1953 onwards, the pass road was sequentially improved and expanded at several sections along the Gotthard route, finally ending in 1977 with the opening of an expressway fully circumventing the Tremola. In winter, however, due to the snow, cars could only cross the Gotthard on the train. Transit time was further dramatically reduced with the opening of the
Gotthard Road Tunnel and the finalization of the northern part of
A2 motorway through the
Urner Reusstal (in close proximity to the railway), with many additional tunnels (then leading from Basel to the Gotthard Road Tunnel), in 1980. With the completion in 1986 of the A2 motorway in the
Valle Leventina, the main valley leading from Airolo down to
Bellinzona, and the surmounting of the
Monte Ceneri between Bellinzona and
Lugano in 1983, finally a continuous motorway was established from the northern border of Switzerland in
Basel to the southern border in
Chiasso, or the shortest motorway route from North-German
Hamburg as far as South-Italian
Sicily, bringing down the competitiveness of the railway line. Passenger speed was also increased on the railway line with the use of tilting trains, notably the
ICN, although maximum speed remaining far lower than on a modern straight high-speed line. Both modern motorway and historic railway rely on heavy rockfall and avalanche protection equipments and are exposed to harsh weather condition in winter. After the opening of the auto tunnel, in 1980, traffic increased more than tenfold. The existing tunnel was at its capacity by 2013. A second tunnel will be built next to the first, following a national referendum. Construction started in 2021 and is scheduled to finish in 2027. As early as 1947, engineer
Eduard Gruner imagined a two-story base tunnel from
Amsteg to Biasca, both rail and road, with a stop at Sedrun, to provide a faster and flatter passage through the
Swiss Alps. Similarly to Gruner's idea, the GBT cuts through the
Gotthard Massif some below the older tunnel. On the historic track only the Gotthard Railway trains up to when using two locomotives or up to with an additional
bank engine at the end of the train are able to pass through the narrow mountain valleys and through
spiral tunnels climbing up to the portals of the old tunnel at a height of above sea level. Since the GBT is in full service, standard freight trains of up to are able to pass this natural barrier. Because of ever-increasing international truck traffic, Swiss voters chose a shift in transportation policy in September 1992 by accepting the NRLA proposal. A second law, the
Alpine Protection Act of February 1994, requires a shift of as much tonnage as possible from truck transport to train transport. The goal of both the laws is to transport trucks, trailers and freight containers through Switzerland, from
Basel to
Chiasso, and beyond by rail to relieve the overused roads, and that of the
Gotthard in particular, by using
intermodal freight transport and
rolling highways (where the entire truck is transported). The GBT substantially contributes to the requirements of both laws and enables a direct flat route from the ports of the
North Sea (notably Rotterdam) to those of the
Mediterranean Sea (notably Genoa), via the Rhine corridor. Although the technical maximum speed is through the GBT, the maximal authorized speed has been reduced to for ecological and economical reasons, while the operating speed of passenger trains is restricted to in order to accommodate the freight traffic, with the possibility to accelerate up to in case of delay. As of 2016, the Gotthard Base Tunnel is the
longest railway tunnel in the world. It is the third Swiss tunnel to bear this title, after the
Gotthard Tunnel (, 1882) and the
Simplon Tunnel (, 1905). It is the third tunnel built under the Gotthard, after the Gotthard Tunnel and the Gotthard Road Tunnel.
Construction AlpTransit Gotthard AG was responsible for construction. It is a wholly owned subsidiary of the
Swiss Federal Railways (SBB CFF FFS). To cut construction time in half, four access tunnels were built so that construction could start at four different sites simultaneously: Erstfeld, Amsteg, Sedrun, and Faido. A fifth at Giornico was added later. The two tunnels are joined approximately every by connecting galleries. Trains can move between the tunnels in the two multifunction stations at
Sedrun and
Faido. These stations house ventilation equipment and technical infrastructure and serve as emergency stops and evacuation routes. The final breakthrough in the east tube occurred on 15 October 2010 at 14:17 +02:00. The final breakthrough in the west tube occurred on 23 March 2011 at 12:20. On 30 August 2013, the tunnel was entirely traversed for the first time from Bodio to Erstfeld in six hours, by diesel train, buses and by foot. On 16 December 2013, the operational test phase started on a stretch in the southern section of the west tube between Faido and Bodio (Giornico). Its purpose was to test the infrastructure and any ancillary systems. On 31 October 2014, the railway track installation was completed. A gold
sleeper on the very last part of the track was installed during the event to mark this milestone of progress. On 1 October 2015, following permission by the Federal Office of Transport, the first tests on the entire length of the GBT were performed, with steadily increasing speed. On 8 November, a train reached the top speed of .
Allocation of work The contracts were awarded in sections: •
Erstfeld (the section from Erstfeld to
Amsteg), with two
tunnel boring machines (TBM) boring the two tubes. The break-through of the east tube between Erstfeld and Amsteg took place on 15 June 2009. The portal area was
surface-mined. • Amsteg (the section from Amsteg to north of
Sedrun), ARGE AGN (
Strabag and Züblin Murer) received the contract for work in this sector. On 9 December 2009, the Amsteg section was officially delivered to the owner for fitting-out, with civil engineering, construction, concrete and lining work completed in early 2010. • Sedrun (the East tube and West tube in the section immediately north and south of Sedrun), along with work performed by Transco (
Bilfinger SE,
Implenia,
Frutiger and
Impresa Pizzarotti). The final breakthrough in the west tube occurred in March 2011. The northbound tubes from Amsteg to the Sedrun multifunction station (north) were handed over to the railway systems contractor Transtec Gotthard on 15 September 2011, the date specified in the construction schedule. •
Faido ( East tube and West tube in the section from south of Sedrun to Faido), with Consorzio TAT (Alpine Mayreder Bau, CSC Impresa costruzioni,
Hochtief and
Implenia and
Impregilo). •
Giornico ( East tube and West tube in the section from Faido to Giornico), with work performed by Consorzio TAT (Alpine Mayreder Bau, CSC Impresa costruzioni, Hochtief, Implenia and Impregilo).
Inauguration and commissioning In 2016, several events, including festivities and special exhibitions, were held around the Gotthard, culminating in the inaugurations in early June, dubbed
Gottardo 2016. Public institutions joined the celebrations:
Swiss Post issued a special
stamp commemorating the Gotthard Base Tunnel, and
Swissmint issued gold and silver coins dedicated to the opening. On 31 May 2016, a day before the inauguration, the nine people who died during construction were commemorated in a ceremony at the north portal in
Erstfeld that was led by a Catholic
vicar general, a vicar of the
Evangelical-Reformed Church of Uri, a Jewish rabbi, and a Muslim imam. A bronze memorial plaque with their names — four coming from Germany, three from Italy, and one from each of South Africa and Austria – was unveiled by AlpTransit Gotthard AG CEO Renzo Simoni. At the northern entrance in Erstfeld, President of the Confederation
Johann Schneider-Ammann spoke of a "giant step for Switzerland but equally for our neighbours and the rest of the continent", while a live relay carried a speech given by Transport Minister
Doris Leuthard at the southern entrance in
Bodio. The first journey carried hundreds of Swiss citizens who had won tickets in a draw, while the assembled guests in Erstfeld, including the Federal Council in corpore, heads of state and government from neighbouring countries and transport ministers from European countries, attended the opening show
Sacre del Gottardo by
Volker Hesse featuring 600 dancers, acrobats, singers and musicians celebrating Alpine culture and
myths around the Gotthard.
Regular services During 2016, the GBT was tested extensively before its integration into the regular schedule on 11 December. On 5 December, the
Swiss Federal Railways were granted permission from the Federal Transport Office to use the new base line. While the base tunnel is used for InterCity trains (
ICN) and EuroCity trains (
EC), the vertex line remains in use for regional trains. Since 2019, the Gotthard axis is served by the
Stadler EC250 (Giruno) high-speed train and future flagship of the
SBB fleet. From the Amsteg portal, guided tours are organised inside the Gotthard Base Tunnel complex. A window allows visitors to watch the trains running in the tunnel.
2023–2024 derailment and closure On 10 August 2023, a freight train derailed while traveling through the tunnel, causing extensive damage to the tunnel infrastructure. The incident occurred near the multi-functional station of Faido, in the canton of Ticino. No one was injured, and no hazardous materials were released. However, the tunnel had to be fully closed to both passenger and freight traffic for repairs. It returned to normal service over a year later on 2 September 2024. ==Politics==