A company (Électricité d'Émosson SA) was created in 1954 to build the dam. The Franco-Swiss development, because of the source of capital, uses different pumping water sites and power generation plants. The construction was decided in April 1967. Previously, a border change was made so that the work was entirely on Swiss territory. Indeed, the border would have cut the dam into two. The communes concerned therefore conducted an exchange of territories, endorsed in 1963. Work began in 1967, and commissioning took place in 1975, eight years later. There was already a first dam on the course of the , the Barberine Dam, owned by
Swiss Federal Railways, for which it was necessary to obtain the authorisation to immerse the earlier structure in the reservoir of the new construction. ==Origin of the waters==