Early history The Couler Creek saw many floods, inhibiting growth in the city in the 19th century. After a flood in 1878, opinion was swayed into directing the Bee Branch into the Little Maquoketa. In 1885, the
Dubuque and Northwestern Railroad acquired right of way along Elm Street and the Bee Branch, leading to an increase of development. Residential development also increased in the Couler Valley as sewers and
streetcars were put in. Another flood in March 1894 brought more calls for the northward diversion. A petition was prepared and, at the time, it was expected to pass unanimously. The chosen idea in the end was putting the creek through a sewer. An advantage of the storm sewer would allow for Elm Street to be expanded. In late 1898, the city council hired J. H. Blake to plan out the sewer. By the mid 20th century, the creek was seen as insignificant. That flood prompted the city to research an engineering project on the
100-year flood area. The
Iowa Department of Homeland Security and Emergency Management (Iowa HSEMD) lists twelve phases. It was found that the storm sewer did not have the capacity for storms of that size.
Detention basins were added or improved on to limit flooding. The creek is more open than its previous sewer design, allowing a greater volume of water to be carried. The project did receive backlash. Citizens were unhappy that homes were getting demolished and they felt that they were not getting compensated enough. Citizens also worried the daylighted creek would be ugly or unsafe or raise utility bills. Construction on the Upper Bee Branch Restoration started in 2015 Six houses, a parking lot, and of soil were removed to make space for the creek. The city also tried to minimize impermeable surfaces causing flooding by converting alleyways into permeable sections. The conversion is expected to cost $9.5 million and be completed in December 2033. to the mid-2010s, In 2017, the Bee Branch adverted a flood when of rain fell. Two more floods were prevented in 2018 and 2019. On June 18, 2020,
Gavilon Grain spilled two containers with a million gallons of liquid nitrogen fertilizer into the Bee Branch. An estimated of fertilizer was spilled into a storm drain that flows into the Bee Branch. The accident was caused by a mistake transferring nitrogen, with the receiving tank overfilling. The transfer was not being watched nor was the spill immediately reported. The company was fined $270,000. It was opened on June 24. This event was commemorated as the finishing the restoration project. However, the Bee Branch Watershed Project is not expected to be completed until 2040. In November 2022, a $3 million project to make a new drainage sewer to replace the temporary
siphon sewer. The siphon system had maintenance issues according to a worker. The city was unable to put in the replacement earlier due to a lack of finances. In 2025, a pump from the
University of Iowa was installed in the Bee Branch, costing $26 million. Work was halted in October on installation over fears of contamination related to the 2020 chemical spill. State and federal contributions have made up the bulk of the funding, with contributions from the city and the Iowa Flood Mitigation Program.
Outcome The Bee Branch after the restoration has been proven to manage flash flooding. However, without all the phases completed, water will move out slower. Overall, the project has prevented $11.6 million in damages. == Geography ==