Early project The discussions on constructing a second nuclear power plant started in the early 1970s. The Belene site was approved for the construction of a second Bulgarian NPP by a
Council of Ministers decree on 20 March 1981. The site was handed to the Ministry of Economics on 31 December 1981 and the documentation for the construction site's preparation was prepared in late 1980 and early 1981 by Energoproekt
Sofia. The site's preparation in accordance with the draft projects began in the early 1981. The foundations of the future power plant were laid in 1987 after the design of Atomenergoproekt
Kyiv from the
USSR and Energoproekt Sofia. The design suggested the construction of four VVER-1000/320 units. Between 1988 and 1990 40% of the construction work on Unit 1 was finished and 80% of the equipment was supplied. The project was abandoned in 1990 due to the fall of communism in Bulgaria and only conservation work was done thereafter. Since then, measures have been continuously undertaken to preserve the supplied equipment, the construction site and the buildings; various investigations and assessments have been carried out with respect to the site suitability and the equipment status, all of which yielded positive conclusions. New investigations have been performed in relation to site safety and its compliance with international requirements. There has been particularly extensive research on the seismic safety of the chosen site. A number of missions were carried out by the International Atomic Energy Agency (IAEA) and other bodies of authority. All these came up with positive conclusions and confirmations that the Belene site is suitable for the construction of a nuclear power plant. The majority of the heavy equipment supplied for Belene's Unit 1 in the late 1980s, including the reactor vessel, was bought back by
Atomstroyexport in 2007 and installed at Unit 4 of the
Kalinin Nuclear Power Plant, which was connected to the grid on 24 November 2011.
Restart In 2002 the Government decided in-principle for a restart of the Belene Project. Fulfillment of all legislative requirements allowed the Government to approve the construction of a nuclear power plant on the Belene site with total rated capacity of 2000 megawatts. The Ministry of Energy began to renew the available equipment and examine the possible construction of the new nuclear plant. In February 2003 Minister
Milko Kovachev sent letters to six leading companies in the sphere of nuclear energy asking them to provide up-to-date technical, economic and financial information regarding the project. A working group of experts was formed by an order of the Ministry of Energy and Energy Resources of 27 May 2003, which included experts from the Ministry of Energy and Energy Resources, the Ministry of Environment and Waters, the Ministry of Transport and Communication, the Ministry of Internal Affairs, the Ministry of Health, the Nuclear Regulatory Agency, the State Energy and Water Regulatory Commission, the State Agency for Civil Protection, the National Electric Company and BulAtom. A programme for the expert commission's work was approved on 4 July 2003. Pursuant to the above-mentioned decision, on May 10, 2005, the National Electric Company launched a procedure for selection of a Contractor for the engineering, procurement, and commissioning of Belene Nuclear Power Plant, Units 1&2. In late October 2006 the offer of the
Russian
Atomstroyexport, the
French Framatome (Areva), and the
German Siemens using third-generation VVER-1000/V-446B reactors was approved by the National Electric Company. The offer was selected due to the highest safety level guaranteed by several new independent active and passive safety systems, as well as the option for Atomstroyexport to buy back the old unit supplied in the 1980s. Another reasons was the 60-year operation term. According to the Atomstroyexport president, the first unit would be in operation by 2013 and the second a year later. On 7 December 2007 the European Commission gave its favourable opinion to the NPP, saying that it met all requirements of articles 41 to 44 of the Euratom Treaty. A favourable opinion of the EC is one of the requirements for a Euratom loan. On 18 January 2008, Atomstroyexport and Bulgaria's
National Electric Company (NEC) signed the contract for the design, construction and installation of units 1 and 2 of the Belene NPP. On 3 September 2008, the construction of the Belene NPP officially started. According to the Minister of Energy Petar Dimitrov, the Belene plant would operate "the most secure reactors existing in the world"; he also asserted that "the chance there would be a failure in those reactors is practically zero". Prime Minister Stanishev and Minister Dimitrov also called the project "a Renaissance for Bulgaria's nuclear energy" and "the largest industrial project in Bulgaria in the last eighteen years". More than 10,000 construction workers would be employed in the project, with the first reactor expected to be operating by the end of 2013, the second by the end of 2014. According to the schedule, Unit 1 of the A92 design has to be erected for 6.5 years and Unit 2 for 7.5 years with consideration of the specific licensing terms as per the Bulgarian legislation. The longest time-consuming activities are related to the design work and equipment delivery (58 months), as well as to the very construction and installation (51 months).
Termination of the project The negotiations stalled again after the
GERB government decided to add an American or a European contractor to the project, as well as insisting for Atomstroyexport to lower the price to less than five billion euro. As no major European or American investor appeared, the talks continued to yield no results. This led to the official termination of the Belene project in March 2012. A thermal power plant using natural gas from the then-planned
South Stream pipeline was proposed to be built on the site, while the reactor supplied for Unit 1 was foreseen to be built as Unit 7 at the Kozloduy NPP. In June 2016, the
International Court of Arbitration awarded
Atomstroyexport €620 million in compensation for equipment already manufactured for the plant, which will be delivered to Bulgaria following payment.
Possible project restart After the election in May 2013 the new Bulgarian government of
Plamen Oresharski (Socialist Party) started to speak publicly about restarting the project. In 2016 discussions took place with
Rosatom, the manufacturer of the reactors, about the possibility of installing one at
Kozloduy Nuclear Power Plant and selling the second one to a third party. An alternative is a privately financed completion of Belene. On 7 June 2018, the Bulgarian Parliament voted to abolish the moratorium on the construction of the power plant. The aim of the government is to complete the project through funding by a strategic investor, what interest has so far been declared by several companies. Minister of Energy should develop an investor selection procedure and propose options for structuring the project by 31 October 2018. According to the Minister, the plant can be completed within 7–8 years. In December 2019, the Bulgarian energy ministry said it had selected five companies among the 13 applications received to participate in the project.
China National Nuclear Corporation (CNNC),
Korea Hydro & Nuclear Power (KHNP) and
Rosatom as potential strategic investors.
Framatome and
General Electric (GE) have also been selected; Framatome expressed interest in providing safety systems, GE offered design and supply equipment, turbines, compressors and transformers. ==Technical features==