Borssele I & II Borssele I & II consists of 94
Siemens Gamesa 8 MW wind turbines for a total capacity of 752 MW. It was built by
Ørsted. The tender for this farm took place in 2016. A total of 38 bids were received. On 5 July 2017, it was announced that Ørsted had won the tender. Construction of the wind farm began in January 2020 and the first electricity was generated in April 2020. By the end of 2020, the construction was finished. The official opening was on 6 September 2021. Ørsted tested
cargo drones in 2024.
Borssele III & IV Consists of 77
Vestas V164 9.5 MW wind turbines for a total capacity of 731,5 MW. Built by Blauwwind II, a consortium of
Shell,
Van Oord,
Eneco and
Mitsubishi. The tender for this farm was held in 2016. A total of 26 bids were submitted. On 12 December 2016, it was announced that Blauwwind II had won the tender.
Borssele V Consists of 2 Vestas V164 9.5 MW wind turbines. The wind farm was built by Two Towers, a consortium of Van Oord Renewable Finance, Investri Offshore and Green Giraffe Holding. == See also ==