The power plant comprises eight CANDU pressurized heavy-water reactors arranged into two plants (A and B) with four reactors each. Each reactor stands within a reinforced concrete containment. The steam generators are 12 m tall, and weigh 100 tonnes each. Each plant uses three fueling machines, shared between the four reactors, which travel in a duct cut through solid rock beneath the reactors, traversing the entire plant. The duct doubles as part of the pressure relief system, connected to the vacuum building. Each reactor has its own turbine generator set, with one high-pressure turbine and three low-pressure turbines driving one generator. The turbine hall is about 400 m long at each plant and houses the four turbine generator sets. Cooling water is taken from Lake Huron.
Bruce A Construction of Bruce A began in 1969, making it the successor to the
Pickering A plant. which was later increased to 769 MWe net / 825 MWe gross. The original Bruce A steam generators utilized a separate large horizontal shared steam drum (with one steam drum common to four steam generators), a design dropped in most other plants at the time. Issues related to the AECL requested design of the tube supports caused repair and delay costs, which exceeded the net worth of the builder
Babcock & Wilcox Canada. Until they were removed in 1998, Bruce A reactors used unique booster rods to control reactivity. Booster rods contained 93%
uranium-235, and were inserted to overcome
reactor poisoning. Bruce B and all other Ontario Hydro reactors instead use absorber rods called "adjusters" which are normally inserted and are removed to overcome xenon poisoning. However, by 2001, when Bruce Power took the lease, all Bruce A units were laid-up. In 1986, maintenance workers accidentally left a protective lead blanket in the steam generator of Unit 2. By the time the mistake was discovered six years later, the blanket had melted, severely damaging the boiler. In October 1995, after about 18 years of operation, unit 2 was taken out of service. Refurbishment in unit 3 began in March 2023, with the plan being to return to service in 2026. In 1990, a software error in unit 4 caused a fueling-machine error, damaging a fuel channel. In 1993, reactor power was reduced to 60% until various
loss-of-coolant accident (LOCA) scenarios could be addressed. Subsequently, Bruce A units returned to 89% of rated power. It returned to service in October 2003, after 6 years of being idle (at which time the unit was 31 years old). and in 2009, Bruce B 5 was first with 95.4% performance.
Bruce B 5 • Construction began 1 June 1978. • On 15 November 1984 it reached first criticality. • On 29 May 1984 it reached first criticality. (unit was 36 years old).
Bruce B 7 • Construction began 1 May 1979. • On 15 February 1987 it reached first criticality. In 2023, it was about 28% of Ontario's production. ImageSize = width:800 height:580 PlotArea = left:50 right:20 top:25 bottom:30 TimeAxis = orientation:vertical AlignBars = late Colors = id:linegrey2 value:gray(0.9) id:linegrey value:gray(0.7) id:cobar value:rgb(0.2,0.7,0.8) id:cobar2 value:rgb(0.6,0.9,0.6) DateFormat = yyyy Period = from:0 till:50000 ScaleMajor = unit:year increment:1000 start:0 gridcolor:linegrey ScaleMinor = unit:year increment:500 start:0 gridcolor:linegrey2 PlotData = color:cobar width:19 align:left bar:2001 from:0 till:24193 bar:2002 from:0 till:21021 bar:2003 from:0 till:24678 bar:2004 from:0 till:33783 bar:2005 from:0 till:33048 bar:2006 from:0 till:36601 bar:2007 from:0 till:35529 bar:2008 from:0 till:35386 bar:2009 from:0 till:34701 bar:2010 from:0 till:36180 bar:2011 from:0 till:36261 bar:2012 from:0 till:35627 bar:2013 from:0 till:45281 bar:2014 from:0 till:45675 bar:2015 from:0 till:46652 bar:2016 from:0 till:45293 bar:2017 from:0 till:49019 bar:2018 from:0 till:48392 bar:2019 from:0 till:46111 bar:2020 from:0 till:43174 bar:2021 from:0 till:42464 bar:2022 from:0 till:42619 bar:2023 from:0 till:42313 bar:2024 from:0 till:45975 TextData= fontsize:S pos:(20,20) text: Bruce Nuclear Generating Station As of the end of 2024, the total lifetime output of the facility was 1,652,901 GWh.
Notable Achievements In 2009 total site output hit 1,002 TWh, making it the first nuclear power plant in the world to produce 1 PWh (1,000 TWh). Gravelines in France achieved the same in 2010. As of the end of 2020, the 8 Bruce units had produced a combined total of 1,479.59 TWh. surpassed now by two South-Korean plants:
Kori NPP since 2019 and
Hanul NPP since 2022. The
Kashiwazaki-Kariwa Nuclear Power Plant in Japan had a larger total output capacity, but it has been out of service since 2011.
Transmission Lines As of 2008, the Bruce station had three
double-circuit 500 kV transmission lines to feed the major load centres in southern Ontario, in addition to three double-circuit 230 kV lines serving the local area. These circuits are connected via two high voltage switchyards owned and operated by
Hydro One. In 2006, OPA had proposed increasing transmission line capacity, at a cost of between $200–600 million, described as "the largest electricity transmission investment in Ontario in the last 20 years". The line was completed in June 2012, several months ahead of schedule, with over 700 towers built for the 180 kilometre line to Milton. The project ranked 45th in Renew Canada's annual list.
Comparison with Pickering Compared to the other major Canadian nuclear power plant built earlier,
Pickering station, the Bruce reactors have higher power output, achieved by: increasing the number of fuel channels, increasing the number of bundles per channel, and a change in the fuel bundle itself. At Bruce, the fuelling equipment is shared by the four reactors of each plant, while at Pickering each reactor had a fuelling machine. The Bruce fuelling machine and fuel channel end fitting design (mostly by
Canadian General Electric) is based on the
Nuclear Power Demonstration design. The Pickering design by AECL was based on Douglas Point. The building design of the reactor differs: Bruce uses a squarish "close-in" design, in which as much of the equipment as possible is arranged outside the main containment envelope for easier access during maintenance and emergencies. Pickering has round domes which enclose much of the secondary cooling equipment. • The Pickering A system did not originally have a second independent shutdown system. The Bruce containment concept differs: the reactor's reactivity mechanism deck serves as a part of the containment boundary, is closer to the reactor, and more prone to damage in the event of an accident ("accidental physical disassembly"). The designers therefore foresaw the need for a second safety system to reduce the risk of an accident. Bruce received a second, fully independent Safety Shutdown System (SDS2) which uses a liquid
neutron poison injection method. • The Bruce system also has a high-pressure Emergency Coolant Injection System (ECIS).
Construction costs Bruce A was projected to cost billion in 1969. Actual cost was $1.8 billion (in 1979 dollars). Adjusted for inflation, the $930 million estimate in 1979 dollars is $1.88 billion, putting Bruce A under budget. Bruce B was projected to cost $3.929 billion in 1976. Actual cost was $5.994 billion (in 1987 dollars). Adjusted for inflation, the $3.929 billion estimate in 1987 dollars is $8.667 billion, putting Bruce B under budget.
Cost of generated electricity In 2010, Bruce Power was paid approximately $60 million for contracted, but unused power. On 1 January 2016, Bruce Power began receiving a single contracted price for all output from the site of per megawatt-hour (MWh). This price is partially adjusted annually to account for inflation and wage growth, with additional monthly fuel cost adjustments, and it includes a small payment for Bruce's unique ability to curtail up to 2400 MW of generation (total across all eight units – up to 300 MW per individual unit) via steam bypass operation during periods of surplus generation. During the course of the refurbishment of Units 3–6, the price will be raised in steps to cover individual reactor refurbishment costs, with each increase starting 12 months prior to the start of each individual refurbishment. Each increase will last only until that unit's refurbishment costs, which are fixed prior to refurbishment start, have been recovered. The average price per MWh that will be paid to Bruce Power for all electricity generated from 2016 to 2064 (covering the entire refurbishment period for Units 3–6 plus the entire expected remaining post-refurbishment lifetimes of all eight Bruce Power reactors (including the two that were already refurbished) was estimated to be approximately /MWh in 2017 dollars by the Financial Accountability Office of Ontario. In contrast, the estimated average price of nuclear electricity from all three Ontario nuclear plants during that same 2016–2064 period was estimated to be /MWh in 2017 dollars, the 2017–2018 unit cost of Ontario nuclear power was /MWh, and the current price of electricity for "most residential and small business customers" was /MWh (prior to the Fair Hydro Plan) or (after the Fair Hydro Plan). "Contrary to popular belief, the electrical generators of nuclear plants can follow the load demands of the electrical grid provided specific engineered systems to permit this mode of operation are included in the plant design."
Cobalt-60 production Cobalt-60 (60Co) can be produced in a CANDU reactor by using adjuster rods made primarily out of 59Co (instead of the normal stainless steel), which is slowly transmuted into 60Co via neutron activation (59Co + n → 60Co). These now-intensely-radioactive cobalt-60 adjuster rods are then "harvested" (removed and replaced with fresh 59Co adjuster rods) after one to three years of use in the reactor during a routine reactor shutdown, and are later processed into sealed 60Co sources of varying intensities by
Nordion. The Bruce nuclear power plant has been producing 60Co since the 1980s, and almost all of the world's supply of 60Co comes from various CANDU nuclear reactors, with Bruce being the single largest supplier. , Bruce supplied over 40% of the world's 60Co. As the NRU produces over two-thirds of the world's HSA 60Co, Bruce's ability to supply HSA 60Co will become critical to help fill the immense production gap left by the NRU once it is decommissioned in 2018. OPG and Bruce Power are collaborating on an effort to expand 60Co production to the Bruce A and Darlington reactors in order to fully cover Pickering's production (which will end when the plant is decommissioned in 2024) in addition to the inevitable gaps in 60Co production capacity that will be caused by the upcoming refurbishments of six of Bruce's reactors (Units A 3–4 & Units B 5–8), as well as all four of Darlington's reactors. In 2017, Bruce Power became the first Canadian recipient of a Top Innovative Practice (TIP) award from the
Nuclear Energy Institute (NEI) for its ongoing work with Nordion to produce cobalt-60.
Radioisotope production project Bruce Power is working with
Framatome to develop the capability to "produce shorter half-life radioisotopes (such as
molybdenum-99,
lutetium-177 and
iridium-192)" using Areva's proprietary technology for the on-line production of radioisotopes in heavy water reactors. Areva will design and supply the system for installation in the existing Bruce units. The initial Isotope Production System (IPS), producing Lu-177, came online in January 2022. ==Refurbishment of Units 1–2, 1995–2012==