Dennis Hastert and former
Architect of the Capitol Alan Hantman tour the CVC during the early stages of construction. Construction of the CVC was supervised by the
Architect of the Capitol. That post was held by
Alan Hantman,
FAIA until his term expired on February 4, 2007; construction was then continued by then Acting Architect of the Capitol
Stephen T. Ayers, AIA, LEED AP. The ceremonial groundbreaking for the CVC took place on June 20, 2000. The proposed cost was originally $71 million, but it has risen to $621 million. The CVC has caused controversy for being over budget and behind schedule. Much of this is blamed on the rising cost of fuel, post-
9/11 security measures, and inclement weather. At a hearing on the CVC cost-overruns Representative
Jack Kingston called it "a monument to government inefficiency, ineptitude and excessiveness." The first major construction contract, worth nearly $100 million, was awarded to
Balfour Beatty (formerly
Centex Construction), in the spring of 2002. This contract involved site demolition,
slurry wall construction, excavation, construction of columns, installation of site utilities, construction of the
concrete and
structural steel, waterproofing, and construction of a new service
tunnel. By July 2005, Balfour Beatty Construction completed all excavation and structural activities, and the roof deck covered the entire CVC structure.
Manhattan Construction Company was responsible for the build-out including, installation of electrical, mechanical and plumbing systems, coordination with existing Capitol building systems where the center connects within the Capitol building, and completion of the above-ground East Front Plaza, with related site work and security elements. ==Operations and features==