MarketCaruachi Dam
Company Profile

Caruachi Dam

The Caruachi Dam is a concrete gravity dam across the Caroní River in Bolivar state, Venezuela. It supports a conventional hydroelectric power facility with 2,160 megawatts of capacity. The dam is approximately 59 kilometres (37 mi) downstream from the Guri Dam belonging to the Central Hidroeléctrica Simón Bolívar, and approximately 35 kilometres (22 mi) from where the Caroni and Orinoco rivers meet at Ciudad Guayana.

The hydroelectric plant
The Caruachi hydroelectric plant () was initially fitted with Kaplan turbine-generators that General Electric supplied for the project and were commissioned in April 2003. The twelfth and final unit entered service on February 28, 2006, and entered into formal/fully commercial operation on 31 March 2006, when the project was officially inaugurated. The total installed capacity is and the power plant produces approximately annually. This project is formed jointly with the Central Hidroeléctrica Simón Bolívar in Guri, Antonio José de Sucre in Macagua and Manuel Piar in Tocoma (under construction), the development of Lower Caroní River hydroelectric resources and one of the world's largest hydro projects now in construction, that, when completed, EDELCA (Electrificación del Caroní CA) claims will save Venezuela the equivalent of 750,000 barrels of oil per day, compared to 300,000 currently. Design and construction The contract for the design, supply and installation of the main electro-mechanical equipment was awarded to a consortium of Kvaerner of Norway, GE Energy of the US, and Elin Transformatoren GmbH of Austria. Major work began on the project in 1998. Following GE's acquisition of Kvaerner's hydro business in 1999, over 90% of the Caruachi contract was carried out by GE Hydro, including all aspects of the design, supply and installation of the turbines, generators, governors, exciters and cranes. A total of 12 Kaplan turbine-generator units, each capable of a power output of 180 MW, were supplied to the project. ABB of Switzerland won three contracts to provide the power transmission system for the project. A 400 kV substation and four related 400 kV transmission lines connect the plant with the country's transmission network. Alstom Power was awarded the contract for distributed control system and SCADA, and small electrical auxiliaries like UPS equipments and DC distribution boards. The original GE Hydro and Elin contracts were, through several mergers and acquisitions, transferred to the 2005-created Andritz Hydro of Austria. While the original Alstom contract was in 2014 inherited by a new GE Renewable Energy entity. == Features ==
Features
A main concrete gravity dam has a maximum height of from its foundations, with an integrated intake structure and powerhouse. A right-abutment rockfill closure dam has a concrete slab face and a maximum height of , and a left-abutment earth and rockfill closure dam has a maximum height of . A spillway with nine spans and radial surface gates has an aggregate flow capacity. A powerhouse is integrated with the main dam with space for 12 generating units () and an assembly bay of . Two transition dams have a intermediate buttress between the powerhouse and spillway. The reservoir has a normal operating elevation of above sea level. == See also ==
tickerdossier.comtickerdossier.substack.com