In the second half of the 1950s, the
E.S.B. built a
hydroelectric power station in
Gweedore. The power station, officially called Clady Power Station, is located in the
townland of Dore, and is just under two miles south-west of where the Clady River leaves Lower Lough Nacung. The station is powered by water diverted from the Clady River. A '
canal' was built to carry the diverted water from the river, as it flowed out of Lower Lough Nacung, to the power station. The 'canal' branches off from the Clady River at the Gweedore
Weir. The 'spent water' from Clady Power Station then flows directly into the Crolly River, also known as the Gweedore River. This power station, which was built between 1954 and 1959, remains in use today. ==References==