On 1 April 2005, the
Nuclear Decommissioning Authority (NDA) became the owner of the site, with the UKAEA remaining as operator. Decommissioning of Dounreay was initially planned to bring the site to an interim care and surveillance state by 2036, and as a
brownfield site by 2336, at a total cost of £2.9billion. A new company called Dounreay Site Restoration Limited (DSRL) was formed as a subsidiary of the United Kingdom Atomic Energy Authority (UKAEA) to handle the decommissioning process. By May 2008, decommissioning cost estimates had been revised. Removal of all waste from the site was expected to take until the late 2070s to complete, and the end-point of the project was scheduled for 2300. Apart from decommissioning the reactors, reprocessing plant, and associated facilities, there were five main environmental issues to be dealt with: • A shaft used for intermediate-level
nuclear waste disposal was contaminating groundwater, and would be threatened by coastal erosion in about 300years. The shaft was never designed as a waste depository, but was used as such on a very ad hoc and poorly monitored basis, without reliable waste disposal records being kept. It was originally used to construct a tunnel for the sea discharge pipe. Later use of the shaft as a convenient waste depository had resulted in one
hydrogen gas explosion caused by
sodium and
potassium wastes reacting with water. At one time it was normal for workers to fire rifles into the shaft to sink polythene bags floating on water. • Irradiated
nuclear fuel particles on the seabed near the plant, caused by old fuel rod fragments being pumped into the sea. In 2012, a two million
becquerel particle was found at Sandside beach, twice as radioactive as any particle previously found. • of radiologically
contaminated land, and of chemically contaminated land. • of high and medium active liquors and of unconditioned intermediate-level nuclear waste in store. • of
sodium, of which are radioactively contaminated from the Prototype Fast Reactor. Historically, much of Dounreay's nuclear waste management was poor. On 18 September 2006, Norman Harrison, acting chief operating officer, predicted that more problems will be encountered from old practices at the site as the decommissioning effort continues. Some parts of the plant are being entered for the first time in 50years. In 2007, UKAEA pleaded guilty to four charges under the Radioactive Substances Act 1960 relating to activities between 1963 and 1984, one of disposing of radioactive waste at a landfill site at the plant between 1963 and 1975, and three of illegally dumping radioactive waste and releasing nuclear fuel particles into the sea, resulting in a fine of £140,000. In 2007 a new decommissioning plan was agreed, with a schedule of 25years and a cost of £2.9billion, a year later revised to 17years at a cost of £2.6billion. , the "interim end state" planned date had been brought forward to 2022–2025. In March 2014, firefighters extinguished a small fire in an area used to store low-level nuclear waste. On 7 October 2014, a fire on the PFR site led to a "release of radioactivity via an unauthorised route". The
Office for Nuclear Regulation (ONR) concluded that "procedural non-compliances and behavioural practices" led to the fire, and served an improvement notice on Dounreay Site Restoration Limited. In 2015, decommissioning staff expressed a lack of confidence in management at the plant and fear for their safety. In 2016, the task of dismantling the PFR core commenced. Plans were also announced to move about of waste
Highly Enriched Uranium to the United States. On 7 June 2019, there was a low-level
radioactive contamination incident that led to the evacuation of the site. A DSRL spokesman said: "There was no risk to members of the public, no increased risk to the workforce and no release to the environment". On 23 December 2019, the NDA announced completion of the transfer of all plutonium from Dounreay to Sellafield, where all significant UK stocks of plutonium are now held. On 20 August 2020, a new date for the site to become available for other uses was announced of 2333, as part of a new draft strategy for reclamation. In April 2023, Dounreay became a division of
Magnox Ltd as part of a simplified operating model for the NDA group. The site licence was transferred from DSRL to Magnox Ltd, and employees at the Dounreay site were transferred from DSRL to Magnox Ltd. In October 2023, Magnox Ltd was re-branded as '
Nuclear Restoration Services', with the Dounreay division referred to as 'NRS Dounreay'.
Framework contracts In April 2019, DSRL awarded six framework contracts for decommissioning services at Dounreay. The total value of these contracts is estimated to be £400million. ==Vulcan Naval Reactor Testing Establishment (NRTE)==