Development The
U.S. Congress passed the Washington Inner Airports Act in 1950 to provide funding for a new airport in the
Washington metropolitan area. This directly led to the creation of what became
Dulles International Airport in
Chantilly, Virginia. and the U.S. government acquired the land that August. The airport was officially named in 1959 after
John Foster Dulles, the
United States Secretary of State under Eisenhower. The airport and its Main Terminal were originally controlled directly by the U.S. federal government
Design The
Civil Aeronautics Administration (CAA) selected
Eero Saarinen of
Bloomfield Hills, Michigan, in May 1958 to design several of Dulles Airport's buildings, including its Main Terminal and control tower.
Ammann & Whitney, who led the airport's overall design, Saarinen and Ammann & Whitney worked in collaboration with the airport's mechanical engineering firm
Burns & McDonnell and the consultant Charles Landrum to collect data for the design of Dulles Airport's Main Terminal. The design team was particularly focused on reducing passengers' walking distances, reducing
taxiing costs, and increasing flexibility of the apron. Furthermore, they anticipated that Dulles Airport would need 60
gates by 1975 to accommodate increasing demand. One early design proposal, by Boyd Anderson of Ammann & Whitney, called for suspension cables between the ground and roof; after Saarinen expressed his satisfaction, the design team instead proposed a cable roof. The terminal itself was tentatively planned to have separate levels for departing and arriving passengers. Contracts for clearing and grading the site had been awarded by the end of 1958, but no contracts for the terminal had been awarded yet. The terminal design was still in progress by early 1959, at which point it was planned to span . The FAA (then known as the
Federal Aviation Agency) announced details of Saarinen's design in January 1960. The plans called for a double-level structure, with concrete piers supporting a concave curved roof; the building could be doubled in size. The
control tower and mobile lounges were designed in conjunction with the terminal; That October, it ordered a prototype of a mobile lounge and awarded a contract for the terminal's telephone service. The FAA also built
settling basins for temporary use until a permanent sewage system for the terminal could be built. The FAA began soliciting bids for the terminal building itself in January 1960 and reviewed the bids the next month. The Corbetta Construction Company of New York City submitted the lowest bid, for $4,432,000, and was subsequently awarded the construction contract. That April, workers began grading the terminal's site and laying
foundations. Models of the Main Terminal were displayed at
Washington National Airport in August 1960. By then, the U.S. federal government (which originally operated the airport) had
oversubscribed all of the ticket counter space and the gates. so outgoing FAA administrator
Pete Quesada postponed the opening date by one year. By June 1961, the airport's original $85 million budget had more than doubled to $175 million, and FAA administrator
Najeeb Halaby said the new terminal would be overcrowded by 1967. Due to a lack of federal funding, the building's initial length was truncated from . at which point it was budgeted at $12 million. The rebar in each column surrounded a metal cage, from which a worker oversaw the pour until it was nearly complete; the cage was then encased in concrete. That November, the FAA awarded a concession for the terminal's bars and restaurants. The FAA paid $4.6 million for the terminal's first 20 mobile lounges that month, By then, the control tower was 60% complete. The airlines agreed to lease the Main Terminal's ticket counter in January 1962, having petitioned for a longer counter. Disputes over fees continued until that June, when the FAA and the airlines agreed on a schedule of operating fees for the mobile lounges and the terminal's space. The terminal's contractors began working double shifts in April 1962 after Halaby threatened to penalize contractors for not completing the terminal by October 1. During mid-1962, the FAA solicited bids for the construction of service spaces for the airlines. Builders had difficulties constructing the windows; Workers eventually built a custom protractor to cut the glass. By then, workers were finishing the interior, while airport staff were practicing with the mobile lounges. As late as a few days before the opening, many parts of the terminal were still incomplete. The final cost was estimated at approximately $16 million. The first passengers began using the terminal two days later, and the terminal recorded 25,000 tourists on its first full Sunday of operation. Some final work was still ongoing, The terminal quickly became a symbol of the new airport, and it received positive acclaim, in part because its mobile lounges made the planes entirely
accessible. Travelers often threw coins into the terminal's reflecting pool; The FAA leased out a
duty-free shop at the terminal in early 1963, and a restaurant opened there that November, at which point the terminal was basically complete. this negatively impacted terminal concessionaires' business.
Newsweek said that staff sometimes outnumbered passengers, Another source said that "a visitor could roll a bowling ball from one end ... without hitting anyone". Conversely, the terminal was popular as a tourist attraction, and the mobile lounges had become more popular than expected; many visitors paid just to ride the lounges. The terminal and airport continued to experience lower-than-expected patronage in the mid-1960s. In 1968, the lower level flooded, causing some damage to the terminal. Patronage steadily increased; by 1969, some concessionaires had recorded their first profits.
1970s and early 1980s By the early 1970s, the FAA anticipated that the terminal's usage would increase sixfold, from 2 to 12 million, within a decade. To accommodate the increased traffic, the FAA ordered additional mobile lounges and stopped giving tourists rides on the existing lounges, Early plans called for the building to be lengthened east–west to , increasing hourly capacity from 1,650 to either 2,300 The architectural firm
Hellmuth, Obata & Kassabaum (HOK) was hired in December 1970 to prepare preliminary designs for the expansion. the project was estimated to cost $12 million. in part because of funding shortages and insufficient demand. The NCPC expressed concerns that the east–west annexes would overshadow the original design, The FAA hired Frank Briscoe Co. in early 1978 to expand the terminal, and work began that September. The same year, the control tower's radome was replaced. HOK's expansion was completed in 1980. By then, customs facilities had been moved to an adjacent temporary structure with four mobile-lounge bays. To attract business, the FAA began allowing small planes to load or unload directly at the terminal itself. Instead, in 1983, the agency proposed a "midfield concourse" in the middle of the apron, from which passengers could load onto planes directly. The first midfield concourse was hastily built and could be accessed only by the mobile lounges.
Master plan expansion Mid- and late 1980s In the mid-1980s, as part of a master plan, a consultant recommended doubling the Main Terminal's size, constructing a people-mover to the midfield concourse, and expanding the terminal's airline gates. New vehicular ramps were proposed to alleviate traffic in front of the terminal. The plans also included new facilities for several airlines that used the Main Terminal, along with a separate terminal for international arrivals. The expansions came amid rapid growth in the airport's usage, which neared 4 million by 1984. at which point was expected to cost $420 million. In the meantime, a clinic, baggage claim areas, and stores in the terminal were added, while the international arrivals area was revamped.
David Childs and Marilyn Taylor of
Skidmore, Owings & Merrill (SOM) were hired to design a master plan for the terminal, which was rapidly approaching its annual capacity of 13 million passengers. Concessions and security equipment had been installed throughout the years, intruding on the original interior design. Security concerns had also required the mobile-lounge docks on the south facade to be closed; instead, passengers had to undergo X-ray screening, creating a
bottleneck. The same year, to alleviate congestion at the Main Terminal, the MWAA began constructing the international arrivals terminal, which was designed by SOM to the west of the original terminal. At that point, the Main Terminal's expansion was scheduled to be completed by early 1994. and a federal inspection area at the Main Terminal was enlarged as well. The International Arrivals Terminal opened in 1991, replacing the international-arrivals facilities in the Main Terminal, though the new terminal quickly became overcrowded. The MWAA was also constructing permanent midfield concourses, replacing the temporary annexes on the main building's southern facade. Despite calls by
United Airlines officials to halt or delay the proposed expansion, the MWAA decided to proceed with the renovation, the cost of which had risen to $319 million. The control tower's radome was replaced again in 1993. or 1997. This was planned to be followed in 1998 by the original terminal's interior. Work on the expansion began in October 1993, though MWAA officials were already contemplating further upgrades before work started. To fund the renovation, the MWAA added a
passenger facility charge to every ticket, The Main Terminal was lengthened to , slightly more than twice the original length, The columns and roofs of the original building were recreated in the annexes, though the annexes' roof cables were prestressed using cranes rather than sandbags.
United Airlines moved into the eastern annex on July 1, 1996, and the annexes were dedicated on September 6 that year. Additional midfield concourses opened in the late 1990s, relieving crowding at the Main Terminal, where queues had frequently doubled back on themselves. Development of the walkway was delayed after U.S. Senator
John McCain withheld congressional funds for the project, stemming from a dispute regarding flights at Washington National Airport.
2000s to present By 2000, there were proposals to renovate the original terminal as part of a $3.4 billion renovation of Dulles Airport. Work on the pedestrian tunnel to concourse B was underway, and several parking garages were being built nearby; in addition, the terminal's control tower was proposed for replacement. An underpass to the new parking garages was completed in 2004 for $81 million, A tunnel for baggage was developed concurrently, and the Z gates opened in 2005. By the mid-2000s, the MWAA was constructing a security checkpoint, along with a people mover (by then known as the AeroTrain) leading to the outlying concourses. and the airport's overall expansion was completed the next year. Additionally, in 2012, checkpoints were added to the Main Terminal as part of the
TSA PreCheck frequent-flyer program, and the MWAA began displaying information on security-screening wait times. The Main Terminal gained direct mass-transit access in 2022 with the opening of Washington Metro's Dulles International Airport station, The MWAA announced another master plan for Dulles Airport in 2025. Renderings of this master plan indicate that a walkway might be built south to midfield concourses A and B. Twenty-one firms submitted plans the next month, many of which incorporated the Main Terminal. == Impact ==