Studies for the UKIrish interconnection date back to the 1970s when the Irish
Electricity Supply Board first examined the possibility of linking the UK and Irish
electricity grids. Further studies were conducted in the early 1990s and a joint study was recently conducted between
Electricity Supply Board and
National Grid plc with the support of the
European Union. In 2004 the Commission for Energy Regulation on request of the Irish Government sought proposals from the private sector to construct two 500MW merchant interconnectors between Ireland and Wales. A private project was established by
Imera Power who was contracted to develop two 350MW interconnectors through its affiliate East West Cable One Ltd. in 2006. In 2006 the Minister for Communications, Energy and Natural Resources, instructed the Commission for Energy Regulation to commence the development of a regulated interconnector of 500MW as it was deemed to be critical infrastructure. Eirgrid commenced work on the East West Interconnector in 2007. It was completed in 2012 and on 20 September 2012 it was inaugurated in
Batterstown,
County Meath by UK
Secretary of State for Energy and Climate Change Ed Davey, Irish
Taoiseach Enda Kenny and
European Commissioner for Energy Günther Oettinger. On 8 September 2016, the interconnector had a fault that occurred during an annual maintenance at the converter station in County Meath. The maintenance was carried out by contractor ABB. The interconnector re-entered service on 20 December 2016 with a fully rated 500MW import, however exports to the UK were still limited to roughly 280 MW. , the cable offered full capacity in both directions. In March 2022, following a planned 3 week shutdown, the interconnector remained at below 1% capacity for an ongoing period. ==Technical features==