In March 2007, newly appointed
United States Coast Guard Commandant Thad Allen announced that the USCG had withdrawn a contract from
Lockheed Martin and
Northrop Grumman for the construction of an initial flawed design of what would eventually become the Sentinel class. In September 2008, Bollinger Shipyards in Lockport, Louisiana, was awarded US$88 million to build the prototype first vessel in its class. That prototype was the first of a projected series of cutters. In September 2008 the series was expected to comprise a maximum of 24 to 34 cutters but by the time the prototype cutter, which became USCGC
Bernard C. Webber, entered service in 2012 the planned number of Sentinel-class cutters had grown to 58. They replaced the 37 remaining aging, 1980s-era 110 ft Island-class patrol boats. and all following Sentinel-class vessels are named after enlisted Coast Guard heroes.
Bernard C. Webber was launched in April 2011, and commissioned in April 2012 at the Port of Miami. She and five
sister ships are stationed in
Miami,
Florida. The second cohort of six vessels is homeported in
Key West, Florida. The third cohort of six vessels is homeported in
San Juan, Puerto Rico. A second contract was awarded on December 15, 2009 for an additional three Sentinel-class cutters at a cost of US$141 million. By April 2010 the Coast Guard's contract with Bollinger allowed for the order of up to 34 Sentinel-class cutters at a cost of up to US$1.5 billion. Even then, the Coast Guard was planning to build a total of 58 Sentinel-class cutters. In September 2013,
Marine Link reported that the Coast Guard had placed orders with Bollinger Shipyards for additional cutters, bringing the number of such cutters ordered by then to thirty. In July 2014, it was announced that the U.S. Coast Guard had exercised a $225 million option at Bollinger Shipyards for construction through 2017 of an additional six Sentinel-class Fast Response Cutters (FRCs), bringing the total number of FRCs under contract with Bollinger to 30. Later that number was increased to 32 cutters. In May 2016, Bollinger Shipyards announced that the U.S. Coast Guard had awarded it a new contract for building the final 26 Sentinel-class fast-response cutters. That brought to 58 the total number of FRCs that the USCG ordered from Bollinger. Acquiring the 58 cutters was expected to cost the federal government $3.8 billion — an average of about $65 million per cutter. By June 2016, 38 of the projected 58 FRCs had been ordered and 17 were in service. The Miami and Key West chorts were complete. The 18th fast response cutter,
Joseph Tezanos, was delivered to the Coast Guard in Key West, Florida, in June 2016 en route to completing the San Juan cohort. On August 9, 2018, the Coast Guard exercised its contract option to order six more Sentinel-class cutters. These would be the 45th through 50th cutters of that class. With this order, the total value of orders under the contract grew to almost US$929 million. On August 21 the 30th fast response cutter,
Robert Ward, was delivered. On July 31, 2019, the Coast Guard exercised its contract option to order another six Sentinel-class cutters. These would be the 51st through 56th cutters of that class. With this order, the total value of orders under the contract grew to about US$1.23 billion. Under the contract, the Coast Guard could order as many as 58 cutters, at a total cost of US$1.42 billion. The six new cutters were expected to be delivered starting in late 2022 and ending in late 2023. In September 2020, the Coast Guard announced it was ordering four more FRCs from Bollinger, to be delivered in 2024. These would be the 56th through 60th cutters of that class. At that time, 40 FRCs had been delivered and 38 had been commissioned. The Coast Guard had recently modified its contract with Bollinger to increase the maximum number of cutters that could be ordered under the contract to 64. The modified contract had a potential value of US$1.74 billion. In 2017, the Coast Guard announced two FRCs would be stationed in
Astoria,
Oregon starting in 2021. In 2018, the Coast Guard announced four more would be stationed in
San Pedro,
California in 2018 and 2019. Also in 2018, the Coast Guard revealed plans to eventually homeport a total of six FRCs in
Alaska, with one cutter in
Sitka, one in
Seward, and two in
Kodiak, joining two already operating from
Ketchikan.
Boston, Massachusetts and
St. Petersburg, Florida would eventually be FRC homeports. In June 2019, the
United States House Committee on Armed Services approved a requirement for the
US Navy to study the possibility of buying a version of the FRC, and basing them in
Bahrain. In 2019
Lieutenant Commander Collin Fox (USN), and columnist
David Axe suggested that, when the
US Navy started to develop unmanned patrol ships to replace the , which are similar in size to the Sentinel class, the hulls and other elements of the robot ships would be based on the Sentinels, and built in the same factory. and deliver the first of the four vessels in the fall of 2024 and the last in the summer of 2025. In 2022, the Coast Guard awarded a $30 million contract to install a fixed pier and two floating docks to accommodate FRCs at
East Tongue Point in Oregon. The first new cutter is expected to arrive at Astoria, Oregon in March 2024 rather than in 2021 as originally planned. In March 2022, President
Joe Biden signed the Consolidated Appropriations Act for Fiscal Year 2022, which provided $130 million in funding for two additional FRCs, bringing the total number to 66. In August 2022, the Coast Guard exercised its contract option for the first of these additional cutters, to be delivered by Bollinger in 2025. This order expanded the total value of the Phase 2 contract with Bollinger Shipyards to US$1.8 billion. In March 2024, a
Congressional Research Service report revealed that the Coast Guard's long term procurement plan called for the purchase of up to 71 FRCs. Six of the new cutters would be deployed to the Indo-Pacific region for engagement with allies and partner countries. On May 8, 2024, the Coast Guard exercised a contract option for two additional FRCs, bringing the total vessels built by or under contract with Bollinger to 67 and the total value of the Phase 2 contract to about US$2 billion. The two new FRCs are expected to be delivered in fiscal year 2028. On September 10, 2025, the Coast Guard announced that it had exercised a contract option for ten additional FRCs, increasing the number of FRCs ordered from Bollinger from 67 to 77. Congress had authorized US$1 billion for this purpose in the
One Big Beautiful Bill Act. These new FRCs are expected to be delivered starting in fiscal year 2028. ==Mission==