By the beginning of planning for the
Interstate Highway System in 1939 (then called the Interregional Highway System), the
Houston–New Orleans–
Mobile corridor was part of the system. Preliminary plans took it along US 90 all the way through Louisiana, serving Lake Charles and Lafayette but not Baton Rouge. By c. 1943, it had been shifted to the north west of New Orleans, using the
Louisiana Highway 12 (LA 12), US 190, and US 61 corridors, and serving Baton Rouge but not Lake Charles or Lafayette. The 1947 plan shifted it to roughly the current alignment, including the long stretch of new corridor across the Atchafalaya Swamp. The corridor was assigned the I-10 designation in mid-1957. Prior to the gaining of federal funding for the Interstate System in the late 1950s, a
toll road, the
Acadian Thruway, had been proposed between Lafayette and a point near
Gramercy on Airline Highway (US 61). This would have provided a shorter route than I-10, bypassing Baton Rouge to the south. The
Gramercy Bridge was later built along its planned alignment, with
LA 3125 connecting to Gramercy, but no road extends west from the bridge across the Atchafalaya Swamp to Lafayette. I-12, serving as a bypass of New Orleans around the north side of Lake Pontchartrain, was not added until October 17, 1957. At the time, I-10 and
I-59 split in eastern New Orleans, with I-59 following present I-10 and I-10 following the US 90 corridor into Mississippi, and so I-12 only ran to I-59 north of Slidell. By the mid-1960s, the routes had been realigned to their current configuration, with I-12 and I-59 both ending at I-10 near Slidell. Construction of the Interstate Highway System in Louisiana began in 1957. Early I-10 contracts were done under the route designation LA 3027. Much of the early construction on the I-10 corridor was concentrated on relieving traffic problems in urban centers. Several such projects were already underway and were incorporated into the route of I-10 during construction, such as the
Pontchartrain Expressway in New Orleans. In addition, the two major bridges on the route in
Calcasieu Parish between the Texas state line and Lake Charles were built for US 90 in the early 1950s and retrofitted for I-10 traffic. Sections of I-10 through rural areas and/or those sections already served adequately by existing highways, such as Airline Highway (US 61) between Baton Rouge and New Orleans, were constructed later in the program. By the spring of 1975, the entire route of I-10 had been opened across Louisiana except for a problem section between
Gonzales and
Sorrento that was not completed for another three years.
Timeline Reconstruction of the portion at the I-610 Split vicinity was undertaken in the late 1990s. Also in the late 1990s, further work was done on the expressway as two ramps were constructed, connecting West I-10 to West Business U.S. 90 and westbound Claiborne Avenue (West US 90), replacing an earlier, more dangerous ramp. The direct ramp from 90B East to I-10 East was completed by 1989. In the aftermath of
Hurricane Katrina, the I-10 Twin Span Bridge, a portion of I-10 between New Orleans and Slidell, spanning the eastern end of Lake Pontchartrain, was severely damaged, causing a break in I-10 at that point. Unlike the
Escambia Bay Bridge (east of
Pensacola,
Florida and damaged by
Hurricane Ivan), which is a major artery, I-12 is available to bypass New Orleans. Taking I-12 to the
Lake Pontchartrain Causeway allowed entry and exit to and from the
Greater New Orleans area from the East. On October 14, 2005, at 3:00 pm, the eastbound span was reopened to two way traffic. On January 6, 2006, at 6:00 am, both lanes of the westbound span were reopened to traffic using temporary metal trusses and road panels to replace damaged sections. This restored all four lanes of the I-10 Twin Span for normal traffic with a speed limit for the westbound lanes and for the eastbound lanes. Oversized and overweight traffic was prohibited until a new permanent six-lane span replaced the two temporarily repaired spans. The eastbound span opened to traffic on July 9, 2009, and the westbound span opened on April 7, 2010, with the old bridge being permanently closed. The approaches to the westbound lanes were completed with a ribbon cutting ceremony on September 8, 2011, and the opening of all six lanes the next morning. The old Twin Span will be demolished in the near future. In 2014, the
Louisiana State Legislature officially named the Twin Span as the
Frank Davis "Naturally N'Awlins" Memorial Bridge. A $68.9 million three-year construction project was completed between
Causeway Boulevard and the
17th Street Canal in
Metairie, Louisiana. It added new lanes in both directions and improve the exit and entrance ramps at Causeway and Bonnabel Boulevard. In 2012, the state completed a widening project between Causeway and Clearview Parkway and between the I-10/I-610 split and Airline Highway (
US 61). In 2015, the additional lanes were extended in Metairie, from Clearview Parkway west to
Veterans Boulevard. I-10 was widened to three lanes in each direction from the I-10/
I-12 split to Highland Road (exit 166) from late 2008 to spring 2013. On April 8, 2017, Louisiana DOTD broke ground on the reconstruction of of I-10 between I-49 (exit 103) and the Atchafalaya Basin. A center concrete barrier was constructed, the road was repaved, and an extra travel lane was constructed, making I-10 three lanes in each direction. Construction began May 2017, was completed in October 2021, and had a ribbon cutting ceremony on November 22, 2021. In order to reduce the amount of congestion for travelers trying to reach the
Louis Armstrong New Orleans International Airport, flyover ramps were constructed at the I-10 and Loyola Drive Interchange in Kenner. Part of the project is constructing a diverging diamond interchange where both of the roads meet as well. The project connected I-10 to the new terminal at the airport that was completed in November 2019 and allowed quick access to a planned station on the proposed
Baton Rouge–New Orleans
Amtrak route on the south side of the airport. Construction began after the terminal was completed and was expected to be completed in November 2022. However, supply chain problems and the damage caused by
Hurricane Ida in
2021 delayed the completion of the project to early-2023. Rainy weather during the Summer of 2022 further delayed the completion of the project to the Summer of 2023. Work on the diverging diamond interchange, which will be the first ever constructed in the state, was not to be started until the completion of the flyover bridges. The I-10 westbound ramp to Loyola Drive was finally opened to traffic on September 29, 2023; the ramp from the airport to I-10 east opened two weeks later on October 13. ==Future==