of the "Suspension Bridge Cincinnati" (from a stamp on the back), taken from Covington looking toward Cincinnati, ca. 1870|left Excavation for the foundation of the Covington tower commenced in September 1856 and went smoothly. A foundation was set consisting of 13 layers of oak beams, each layer set perpendicular to the one beneath it, bolted with iron hardware, and finally all cemented into place. On the Cincinnati side, work was delayed from the start. The construction crews could not pump water out of the excavating pit fast enough. After months of little progress, Roebling decided against buying costly machinery or bigger engines for his pumps and, quite last minute, designed his own square
positive displacement pumps from three-inch (76 mm) pine planks. He built them locally in about forty-eight hours and ran them off of one of Amos Shinkles'
tugboats, the
Champion No.1. The homemade pumps displaced forty
gallons of mud and clay in each cycle. When the crews reached the compacted gravel bed of the Ohio River, Roebling decided this would be sufficient for the foundation of the Cincinnati tower. Oak timbers were laid, mirroring the foundation of the Covington tower, and within three months, masonry on both towers reached above the waterline (which, at this time, was at a record low for the fall). Work halted for the freezing temperatures and increased water level, a practice which continued seasonally until completion of the bridge. At this time, a revised contract was drawn up, stating work was to be completed by December 1858, barring "unavoidable calamities". After a hard winter of 1856–57, and a wet spring, construction resumed in July 1857.
Sandstone was used for the first twenty five vertical feet of each tower base.
Limestone encased this sandstone to protect against
scour and collision from watercraft. The remaining height of each tower was to be constructed of sandstone, rough cut and with a large draft. Roebling said this gave the towers "a massive look, quite suitable to their function." Working from July to August 1857, the company was without liquid funds, a problem compounded by the
Panic of 1857. Work halted because of the inability to pay for the project. In July 1858, operations resumed again, albeit with a smaller workforce. Only one tower was worked on at a time. President Ramson of the company died, and no work was done during the years 1859–60. In November 1860,
Abraham Lincoln was elected president of the United States, and the
Civil War began in January 1861. Upon a threatened siege of Cincinnati from Confederate forces, a
pontoon bridge was built to span the Ohio River, allowing Union troops to cross and construct defenses. Soon after, once it had become obvious that a permanent structure was vital, money from investors came pouring in. Bonds were sold, and in January 1863 materials began arriving. In the interest of building more quickly, the requirement for the height of the main span was lowered to . Preparations to resume construction were made. Machinery was ordered, and new derricks were built, but a renewed threat of invasion again temporarily halted progress. Finally, in the spring of 1863, work commenced and continued until the end of the year.
finials. The
U.S. and
Ohio flags are displayed in the center. In the spring of 1864, work resumed again. Although Roebling operated his own wire mill at
Trenton, New Jersey, the bridge company purchased one million pounds of wire from Richard Johnson at
Manchester, England, for the cables that would span the width of the river. Roebling had used Johnson's wire for one of his other bridges. He preferred it over wire made in the United States because it was of better quality and greater
tensile strength. Anchorages on both shores were constructed of limestone base and a
freestone finish. Eleven-ton iron anchors were embedded in each block, securing cables with wrought iron chain links of Roebling's patent. The Civil War depleted the work force on the project, hindering speed and efficiency until its end. Work on the bridge proceeded steadily after the end of the war. In September 1865 the first two wire ropes were laid. They were unwound from a spool on a barge, allowed to sink to the bottom of the river, then raised in unison from the riverbed. Wooden crossbeams were laid at regular intervals from the wire ropes, and a simple footbridge was constructed for the benefit of the workers. With the Ohio River "spanned," there was a final push to complete the project even through floods and freezing temperatures. The cabling of the bridge went at a feverish pace, with about eighty wires placed per day. Hundreds watched the spider-like process from both shores. And on June 23, 1866, the last wire was taken across, for a total of 10,360 wires. These were subsequently compressed together and wrapped with an outer covering of wire into two cables of 5,180 wires each. Suspenders were hung from the cables by the end of August, and of oak lumber was laid as the deck across 300 wrought iron suspended beams. Two tracks for streetcars were laid. Diagonal stays were added to increase load capacity, strengthen the floor, and
check vibration. Wrought iron trusses were added, running the length of the bridge. On December 1, 1866, pedestrians walked upon the bridge, known locally only as "The Suspension Bridge," for the first time. Over 166,000 people walked across in the first two days. Final touches were put on the bridge over the next few months, and construction officially ended in July 1867. Two men died during construction. When the Roebling Bridge was formally opened on January 1, 1867, the driver of a horse and buggy was charged a
toll of 15 cents to cross; the toll for three horses and a carriage was 25 cents. Pedestrians were charged one cent. The bridge was repainted blue in 1894. The original deck of the bridge was built at the lowest possible cost because of Civil War inflation, but the stone towers had been designed to carry a much heavier load than was originally demanded. In 1896, the bridge received a second set of main cables, a wider steel deck, and a longer northern approach. The reconstruction significantly altered the appearance of the bridge, but the new 30-ton weight limit extended its usefulness through the 20th century and beyond. In 1901, electric lighting was added to the bridge. In 1918, an extension of the approach was completed to Third Street. At the time the Suspension Bridge was built, the
Ohio River was very shallow, often only a few feet deep. A 100-foot vertical clearance was important as steamboats had high stacks to keep sparks as far as possible from the rest of the wooden craft. As more railroads were built and barges replaced steamboat traffic, dams to raise the river and control flooding made sense. In the early 1900s Congress authorized a system of locks and dams along the Ohio River. In 1929, the canalization project produced 51 wooden wicket dams and lock chambers along its length. This system assured that the depth of river at Cincinnati never fell below 9 feet. During the 1940s, a shift from steam propelled to diesel powered towboats allowed for longer barges than could be accommodated by the existing dams. In the 1950s the
US Army Corps of Engineers replaced the outdated system with
new non-navigable dams made of concrete and steel. These dams raised the height of the river at Cincinnati to a normal pool of about 26 feet, lowering the clearance of the Roebling Suspension Bridge to around 74 feet. The Covington-Cincinnati Bridge Company—a private company—operated the bridge until the Commonwealth of Kentucky purchased it in 1953 for $4.2 million. Soon after this, the bridge was redecked to have a steel deck instead of the previous wooden one. When streetcar service ceased in the 1950s, the ramps onto the Dixie terminal were rebuilt to be used by diesel buses. The state collected tolls until 1963 when the
Brent Spence Bridge was opened on
Interstate 75, downstream, approximately to the west of The Roebling Suspension Bridge. In the fall of 1966, the bridges 100th anniversary was celebrated with a parade at Court Street. Initially called the "Covington-Cincinnati Suspension Bridge" or "Ohio River Bridge", it was renamed in honor of its designer and builder on June 27, 1983. It was designated a
National Historic Civil Engineering Landmark the same year. In 1984, at the cost of $200,000, the bridge had lighting installed on its cables. They also later restored its sprails at the cost of 10 million. It reopened in late March. However, it closed again for much of 2008 for repainting. On September 11, 2007, the Commonwealth of Kentucky reduced the weight limit to 11 tons to prevent future structural damage following an analysis by the
University of Kentucky. The lower weight limit prevents buses from crossing the bridge. The Commonwealth of Kentucky once again closed the bridge on April 7, 2010, for repainting; the bridge reopened in November 2010. The closing of the bridge only affected vehicular traffic, while one pedestrian lane remained open. On January 10, 2013, a large piece of sandstone fell from the north tower causing the bridge to be closed for approximately 4 hours during rush hour. This time was used to remove debris and inspect the tower for further damage. On March 21, 2018, the bridge was closed until April 27 after an automobile accident damaged a steel section of the bridge. On April 17, 2019, another piece of sandstone fell, prompting closure until August 9. On November 11, 2020, the nearby
Brent Spence Bridge was closed following a fiery collision. Semitrucks began using the Roebling Bridge as an alternate crossing point, in violation of the bridge's 11-ton weight limit, prompting Covington police to close the suspension bridge to all vehicular traffic so additional safeguards could be put in place. The Roebling Bridge reopened on November 13, 2020, with Covington and Cincinnati police monitoring traffic on the bridge. On February 15, 2021, the bridge closed for a nine-month rehabilitation project; it reopened in November 2021. ==See also==