In June, 2012, authorities reopened most of the of the river that had been closed to recreation after the spill. Part of the river at the Morrow Lake delta remained closed and other sections of the river remain restricted because of the ongoing cleanup of the
oil sands product called
diluted bitumen (dilbit) the pipeline had been transporting. The
United States Department of Transportation summer 2012 "fined Enbridge $3.7 million dollars and as part of that fine they listed 22 probable violations that happened relating to the spill. And several of those [violations] are about what happened in the [Edmonton] control room". In July 2016, Enbridge agreed to pay $177 million in penalties and improved safety measures in a settlement with the
U.S. Justice Department and the
Environmental Protection Agency.
National Transportation Safety Board investigation In July 2012, the
National Transportation Safety Board, the U.S. federal agency with regulatory authority over the failed pipeline, issued a report representing the official conclusion of the investigation into the incident. The investigators found that the operating firm, which had received an automated signal from the pipeline that a breach had occurred, misunderstood or did not believe the signal and attempted to continue to pump dilbit oil through the pipeline for 17 hours after the breach. Local firefighters were notified, and tried to locate the southern Michigan wetland site of the breach, but were initially unable to do so, further delaying the shutdown of the line. NTSB Chair
Deborah Hersman likened "Enbridge's poor handling" of the spill to the
Keystone Cops, asking: "Why didn't they recognize what was happening, and what took so long?"
NPR reported that "NTSB investigators determined that the gash in the pipe was caused by a flaw in the outside lining which allowed the pipe to crack and corrode. Now, in 2005, Enbridge actually had learned that this section of pipe was cracked and corroding. ... That same 2005 internal report pointed to 15,000 defects in the 40-year-old pipeline. And Enbridge decided not to dig up this [Talmadge Creek] area to inspect it." In 2013, in opining on the
Keystone XL pipeline proposal, the EPA recommended to the
State Department that pipelines that carry bitumen should no longer be treated just like pipelines that carry any other oil. Stephen Hamilton, an ecology professor at Michigan State University and the independent science adviser at Talmadge Creek, detailed the challenges and expense of the still-ongoing Michigan cleanup.
Additional dredging under 2013 order The EPA issued an Order for Removal in 2013 which required Enbridge to remove oil-contaminated sediment from specific locations along the Kalamazoo River, including the three areas where submerged oil was most pronounced: • Upstream of the Ceresco Dam (along Riverside Farm) • Mill Ponds area • Morrow Lake, Morrow Lake Delta and adjacent areas • Sediment traps at two designated locations By the fall of 2014, Enbridge had completed the remaining obligations under the 2013 Order for Removal, including the dredging of oil-contaminated sediment. Based on the successful completion of the work by Enbridge, the EPA transitioned the oversight of the remaining obligations to the Michigan Department of Environmental Quality in 2014.
Safer oil and gas transportation; renewable energy One of the results of the Enbridge spill into the Kalamazoo River is that two fossil fuel companies with operations in the
Kalamazoo, Michigan area have additional technology in use to assist oil and gas that is transported. These same two companies, Wolverine Oil and Gas and the Anton Williams Holding Company of
Kalamazoo, Michigan and have also increased their usage of renewable energy in operations in
Kalamazoo, Michigan. == Gallery ==