Planning and construction The
Sengkang estate was first earmarked for development in the
Urban Redevelopment Authority's 1991 Concept Plan. At the groundbreaking ceremony of the
Bukit Panjang LRT line on 27 September 1996, deputy prime minister
Tony Tan announced the government's decision to construct the Sengkang LRT (SKLRT). The line would be developed alongside the
Sengkang estate and integrated with future developments, intended to improve accessibility and convenience for residents. An exhibition for the SKLRT opened on 7 December 1996 in
Ngee Ann City. At the time, according to communications minister
Mah Bow Tan, the SKLRT was planned to be completed in 2002. The contract for the design and construction of the Sengkang and
Punggol LRT lines was awarded to a joint venture on 4 July 1998 for S$656 million (US$ million On 20 May 1999, Singapore Bus Service (later renamed
SBS Transit) was appointed to operate the SKLRT along with the
North East Line and the Punggol LRT line. Construction of the SKLRT stations and viaducts was completed in 2001. In December of that year, subcontractor BRR Holdings withdrew from the LRT project due to financial difficulties, and handed over its responsibilities to SembCorp Engineers and Constructors. According to Singapore's transport agency – the
Land Transport Authority (LTA), the withdrawal had minimal impact on the construction schedule. On 1 September 2002, the LTA transferred operations of the SKLRT to SBS Transit, which conducted extensive test runs and trials on the line. This came in light of frequent delays and breakdowns experienced on the Bukit Panjang LRT. In December 2002, transport minister
Yeo Cheow Tong said the opening of the SKLRT would be delayed due to modifications required for the communication and radio systems. Due to limited funding from the
1997 financial crisis and low projected ridership, the Sengkang LRT line was initially constructed for single-car operations, even though it had been designed for two. Nevertheless, provisions were made for future upgrades to two-car operations during the expected equipment replacement cycle within 15 to 20 years.
Opening The east loop commenced operations on 18 January 2003, offering free rides during its first two days. The system experienced its first breakdown on 5 September that year because of a computer failure. In October 2004,
Today reported that the SKLRT was operating at a loss due to low ridership, as only 37,000 of the projected 95,000
public flats had been completed. With the exception of the Farmway, Cheng Lim, and Kupang stations, To mark the commencement of the west loop, Wee Siew Kim, Adviser to Jalan Kayu Grassroots Organisations, officiated the opening of the bridge linking Thanggam Station to
Jalan Kayu via Lorong Samak. On 4 January 2010, the west loop commenced bidirectional services only on weekday peak hours from 6:45am to 9:00am and from 6:15pm to 8:30pm. Kupang station opened on 27 June 2015 to cater to new residential developments in its vicinity. Daily ridership on the SKLRT at the time had reached 60,000. A power trip caused a two-hour disruption on the evening of 1 June 2016. On 16 February 2018, a dislodged power collector shoe caused a train to stall near Sengkang station. On 9 June 2024, the signalling system's power supply failed during upgrading works. As a result, no trains could be launched on that morning, with services only resuming at 10:12am.
Upgrades On 31 October 2012, the LTA announced plans to increase passenger capacity of the Sengkang and
Punggol LRT lines (SPLRT) to cater to increased ridership on the SPLRT.
The Straits Times reported in September that the LTA had completed engineering studies for upgrading the system from one-car to two-car operations. The upgrading works involved retrofitting 16 of the 41 one-car trains for two-car operations while purchasing 16 additional cars. Two-car operations on the SKLRT began on 22 December 2015, However, in October 2024, Sengkang GRC Member of Parliament (MP)
Jamus Lim highlighted commuter concerns about inconsistent train frequencies and the irregular use of two-car trains during peak hours. These works included power rail and signalling maintenance, along with reinforcing viaduct crossheads and replacing bearings after cracks were found during inspections. The maintenance works took place on selected Sunday mornings from 14 January to 25 February 2018, during which the affected loops operated unidirectional services. Rectification works on the concrete plinths and elevated slabs were conducted on Sunday evenings between May 27 and October 7. Maintenance works during service hours continued in 2020, 2021, and 2022. Although these works were originally scheduled for completion in 2022, the LTA announced in 2021 that the renewal had been delayed due to the impact of the
COVID-19 pandemic. Plans to refurbish Sengkang station was announced in May 2018. The upgrades included expanding the LRT platform and installing new dual-speed escalators and a new lift to connect the platforms, concourse and mezzanine levels of the station. New signs and queue markings were introduced on the platform to indicate new stopping points for each of the four LRT routes plying the station. The refurbished LRT platforms began operations at the end of September 2024. On 5 February 2021, the LTA said they would purchase 17 two-car trains for the SPLRT, which were expected to be delivered from 2024 to 2027. The
Sengkang Depot would also be expanded to to increase capacity and maintenance space for the new trains. The depot expansion also included two new reception tracks to reduce train launching time. In February 2022, the contract for the depot expansion was awarded to Sato Kogyo (S) Pte Ltd for S$157 million (US$ million), and the contract for the new fleet of trains was awarded to Mitsubishi Corporation for S$439 million (US$ million). ==Network and operations==