A connection between Leipzig Hauptbahnhof and Bayerischer Bahnhof was first considered in 1892. The implementation was planned as an underground railway, running parallel to the two mainline tracks from Borsdorf via the Hauptbahnhof and the Bayerischer Bahnhof and on to Connewitz and Gaschwitz. It would be powered by a
Third Rail system. During the construction of the main station (started in 1909), between 1913 and 1914 a 140m long entrance ramp was built from the direction of Dresden with a 675m long tunnel under part of the station. The tunnel ended 8.5 m in front of the station building under the
inner city ring road. Beneath the current tram and bus stops, underground platforms 22 and 23 of some 40m in length were built. An extension below the ring road was planned and prepared to a length of 100m. The construction work was suspended during
World War I and was not resumed thereafter. During
World War II the tunnel and underground stop were converted to provide
air-raid shelters. During the bombing raid on Leipzig on 7 July 1944, there were two explosions that destroyed the tunnel at two places and thus divided it into three parts. During reconstruction of the main station, the area around the second impact point was walled-in, and the platform under the east portico converted into the
DEFA-Zeitkino Cinema and was used for this purpose until 1992. During the redevelopment of the main railway station in the years 1995 to 2000, parts of the tunnels under the station were demolished. The tunnel below the apron and the first few metres of the station hall were closed, but remained preserved. Shortly after World War II, in 1946, planning for an underground city crossing restarted. In order to accommodate the entrance of the tunnel, redevelopment work at the corner of Windmühlen- and Grünewaldstraße was delayed. That would allow a curve to be built with a suitable arc for long-distance trains. The plan foresaw an S-Bahn route and a mainline railway tunnel in the direction of Munich. The latter was dropped a few years later due to the
division of Germany. By 1967 three variants for the S-Bahn tunnel had been developed which, together with the current tunnel, no longer ran in the direction of the Dresden route, but rather in the direction of Magdeburg and Berlin. Stations were planned under the Western Hall of the Hauptbahnhof and under the city-centre Markt. Due to the expected high financial and technical effort, the plans were not realized before the end of the
GDR.
Planning The tunnel is used by 6 out of 7
S-Bahn Mitteldeutschland lines. It is hoped that shorter intervals and faster connections will allow
public transport to carry more passengers and thereby relieve road traffic in the city. In addition, it will bring more passengers directly by rail from Leipzig Hauptbahnhof to the city centre and convert the
terminus to a partial through-station. Additionally, it was planned to run one intercity train per hour in each direction through the tunnel. However, until December 2012 the
electrified route ended in
Reichenbach im Vogtland. Therefore, the states of Saxony and Bavaria, the Federal Government and DB were planning to continue rail electrification first to
Hof, and later on to
Regensburg and
Nuremberg. The
section to Hof was fully electrified by 15 December 2013. Early in 2002, the Saxony State Government gave support for the implementation of the City Tunnel. On 18 March 2003, they approved the project formally. On 6 January 2010 a correction notice to the tender for the Leipzig train network was issued, announcing that the start of the new train service would be delayed for another year until the timetable change in December 2013.
Costs The 2002 framework agreement foresaw the total project cost as €571.62 million, financed by funds from the State of
Saxony (€182.02 million), by the European Union (
ERDF programme, €168.73 million), the Federal Government (€191.73 million),
Deutsche Bahn (€16.36 million) and the City of Leipzig (€12.78 million). This agreement covered many issues, including the refurbishment of the stations and the electrification of several sections. The contractor's representatives
DEGES expected the costs in December 2006 to amount to 585 million euro. A risk analysis by Deutsche Bahn saw at that time possible additional costs of up to 73 million euro. In December 2007, the additional cost was estimated at 133 million euro, so that the expected total cost will be 705 million €. After the estimated total costs had risen by the end of November 2009 to 893 million euro, the state auditors of Saxony reviewed the project. At the end of February 2010, a further cost increase to 960 million Euros was announced. According to the State of Saxony, this remains the expected total cost (). In the early 1990s the plans for a public transport tunnel through central Leipzig, which had existed for decades, were presented together with the results of new planning in 1995. In 1996 the DB and the Land of Saxony, expressed their support for the project. In the same year the Land, City Planning and DB AG Company founded the planning company
S-Bahn Tunnel Leipzig GmbH. Following a
cost-benefit analysis in 1998, a planning application was issued. In 2000 planning approval was granted. In the autumn of 2001, Saxony invited DB to be the owner of the City Tunnel project. The company was therefore expected to build the tunnel on its own financial risk. the invitation of the individual building sub-contracts took place. On 9 July 2003, the construction began with the official groundbreaking. At the start of the construction process, the tunnel was planned to be in operation by late 2009. Initial activities mainly consisted of ground investigations and the relocation of services. The construction of the underground stations began in early 2005. At the end of March 2005 preparations for building the platform area of the main station began. This space was created for the following excavation. In December 2006, the construction of the ramps at the main station was interrupted after cracks were found in neighbouring station buildings. Between 17 February and 25 March 2007 two auxiliary bridges of 105 m were built as part of the construction in the Central Station. In addition 1,400 metres of track and eight sets of points were rebuilt. On 11 January 2007 the tunnel boring machine called
Leonie began (with a ceremony at the Bayerischer Bahnhof) to symbolically bore the first tunnel. The tunnel's godmother is Angelika Meeth-Milbradt, wife of then Prime Minister of Saxony
Georg Milbradt The excavation began on 15 January 2007 and on 10 March 2008 reached the railway station, so completing the first bore. After the return of the tunnel boring machine to Bayerischer Bahnhof in late March 2008, the excavation began of the second bore on 9 May 2008. On 31 October 2008, the tunnel boring of the tunnel ended with the completion of the second bore. Ahead of the expected opening in December 2013, activities centred on the interior fitting-out of the tunnel and railway stations. In mid-February 2009, the contract to develop the five stations was advertised throughout Europe. The contract ran from February 2010 to November 2011. The tender has been divided between two companies. ==Construction technique==