The line was built by the
Leipzig-Dresden Railway Company (
German:
Leipzig-Dresdner Eisenbahn-Compagnie,
LDE) established by twelve businessmen in 1835. The idea that a railway should connect
Leipzig with
Strehla (on the
Elbe), was first suggested in 1830 by the Leipzig merchant Carl Gottlieb Tenner. After the economist Friedrich List (1789–1846) published plans in Leipzig in 1833 for a German railway system with Leipzig as a central node, Tenner's idea gained new force. In the same year, a railway committee was established and it addressed a petition requesting the building of a railway line from Leipzig to Dresden to the first
Saxon parliament (
Sächsischer Landtag) in Dresden on 20 November 1833. with departing steam engine, around 1837 After the railway had been approved by government decree on 6 May 1835, the Leipzig-Dresden Railway Company was founded by twelve citizens of Leipzig as a private corporation on 22 May. The shares of the company were fully subscribed at a price of 100
thalers within one and a half days, making capital of 1.5 million thalers available to the company. In October 1835, the English engineers
Sir James Walker and Hawkshaw examined the proposed routes and stated their preference for a northern route via Strehla (estimated cost: 1,808,500 thalers) rather than a route via
Meissen (1,956,000 thalers).
Construction about 1840 On 16 November 1835, land acquisition began for the section between Leipzig and the bridge over the
Mulde west of
Wurzen. Ground was broken near
Machern on 1 March 1836. The management of the construction for the whole project was in the hands of the Saxon Senior Waterways Construction Engineer (
Oberwasserbaudirektor), Karl Theodor Kunz (1791–1863). But then the town of Strehla refused permission for the railway to be built through it. So the line was built seven kilometers to the south, crossing the Elbe in Riesa. The company's initial capital in 1837 was 4.5 million thalers, which was later increased to 6.5 million thalers. The first train crosses the Elbe bridge on 7 April 1839. The line was brought into operation in several stages: • 1837, 24 April: Leipzig–Althen (10.60 km) • 1837, 12 November: Althen–
Borsdorf–Gerichshain (4.32 km) • 1838, 11 May: Gerichshain–Machern (2.93 km) • 1838, 19 July: Weintraube–Dresden (8.18 km) • 1838, 31 July:
Machern–Wurzen (8.00 km) • 1838, 16 September:
Wurzen–
Dahlen (17.53 km) • 1838, 16 September:
Oberau–
Coswig–Weintraube (13.44 km) • 1838, 3 November: Dahlen–
Oschatz (9.56 km) • 1838, 21 November: Oschatz–Riesa (13.07 km) • 1839, 7 April: Riesa–Oberau (28.45 km) On 7 April 1839, on the completion of the Elbe bridge at Riesa, the entire route from Leipzig to Dresden was finally opened. The travel time between Leipzig and Dresden was three hours and 40 minutes. It included the 513-metre-long Oberau Tunnel, the first standard gauge rail tunnel in continental Europe. The line was preceded only by the
Prince William Railway, a
narrow-gauge plateway opened in 1831 and the
Bavarian Ludwig Railway opened in 1835, which was a short line and was initially operated largely by
horse-drawn trains, partly because it was located a long way from coal fields and no railways existed to convey coal to
Nuremberg. In contrast the Leipzig–Dresden Railway used only
steam traction from its beginning. Work began immediately on building a second track. The whole line was open for two-track operations by 1 October 1840. This was made possible because the subgrade along with all engineering structures had been designed from the outset for two tracks. Trains—following English practice—ran on the left until 1884.
Operations by the Royal Saxon State Railways On 29 March 1876, the general meeting of shareholders decided to sell the Leipzig–Dresden Railway to the Saxon government. Operations and management of the Leipzig-Dresden Railway were transferred to the
Royal Saxon State Railways (
Königlich Sächsische Staatseisenbahnen) on 1 July 1876. The development of the Leipzig–Dresden Railway from its beginnings as a private initiative of Leipzig citizens until its nationalisation in 1878 is reflected in Leipzig's railway heritage. The Saxon part of the new
Leipzig Hauptbahnhof (main station), which became the terminus for trains from Dresden, was put into operation on 4 December 1915.
After the First World War 1 April 1920, the
Royal Saxon State Railways (recently renamed the
Saxon State Railway) were absorbed into the newly established
German National Railways (
Deutsche Reichsbahn). The Leipzig-Dresden line came under the administration of the
Dresden Reichsbahn Directorate. From 1 July 1933 to July 1934 the Oberau Tunnel was opened up and turned into a cutting, because the tunnel was not wide enough as the
loading gauge had increased. As a result, the distance between the two tracks did not allow two trains to pass in the tunnel.
The line in the communist era In 1946 one of the two tracks was removed to provide the route as
reparations to the
Soviet Union. Even the previously four-track section between and was reduced to only one track. This meant that the capacity of one of the most important main lines in Germany had been reduced to only a fraction of its former level. Temporarily trains ran one way from Leipzig and Dresden on the line, while trains running in the other direction ran via
Meissen and Döbeln. This system of operations proved problematic, however, as the hilly route via Döbeln meant that additional locomotives were always needed for heavy trains. The second track had been rebuilt by 1967. The table below shows the dates of the completion of the electrification:
Upgrade to a high-speed line After the
German reunification in 1990, the line was one of the busiest railway in Germany and, like many other lines of Deutsche Reichsbahn, required urgent rehabilitation and modernisation. The project was approved as German Unity Transport Project No. 9 (VDE 9) by the
Federal Cabinet on 9 April 1991. The scheduled journey time between
Leipzig Hauptbahnhof and
Dresden Hauptbahnhof has been reduced to 47 minutes in 2014. In 1990, the travel time between Leipzig and Dresden had been 90 minutes.
Planning The
Reichsbahn divisions of Dresden and
Halle developed a feasibility study until 14 November 1991. Initially it was planned that the existing route would be supplemented by about 105 km of new line. With a top speed of 250 km/h, the travel time of ICE trains would have amounted to around 35 minutes. The completion was initially scheduled for 31 December 1998. With 74 km of upgraded line and 41 km of new construction, the line would be able to operate over its entire length at 200 km/h. An application for planning approval for the new section was prepared in 1993. A scheduled rebuilding of the line between Engelsdorf and Leipzig as a four-track electrified line was rejected by the Federal Ministry of Transport on 27 August 1993. The preparatory work for the construction of this section, which had started in May 1993, was abandoned. The
Weißig–Böhla link to the Berlin–Dresden railway and the diversion of long-distance services to the Berlin–Dresden line between Böhla and
Neucoswig represented the only remaining planned changes to the route of the line. To date (as of 2013), no completion date has been set for the entire project In addition, a 7 km-long 110 kV traction current cable between Lüptitz and Wurzen and the Wurzen substation was to be rebuilt • upgrade of the Leipzig–Riesa section for a top speed of 200 km/h. This stage was started in 1993 and completed in 2002. In 1996, the first
electronic interlocking in Saxony was taken into operation in Oschatz. The line has been largely upgraded for speeds of 160 km/h in the city of Leipzig and for 200 km/h east of Leipzig-Paunsdorf. In the section between Leipzig and Wurzen the existing route has been largely preserved; deviations of the line were necessary in four places to permit speeds to be raised. The section of rebuilt line through Wurzen station (km 21.6 to 27.66) was upgraded for speeds of only 160 km/h. In the autumn of 1997, the
Posthausen–Altenbach and Wurzen–Bornitz sections were upgraded for operations at 200 km/h, services commenced on the Borsdorf–Altenbach section at 160 km/h and on the Wurzen-Riesa section at 200 km/h in May 1998. The upgrade of the Altenbach–Wurzen section (km 21.64 to 25.23) started in the autumn of 1999, including a realignment around the Mulde, which was around 1,000 m long. The first stage of construction between Leipzig and Riesa went into operation in 2002. The section has since been largely (kilometres 5–23 and 29–51) operable at 200 km/h and equipped with the
Linienzugbeeinflussung train protection system (kilometres 3.6–59.5). Between Borsdorf and Bornitz the sub-block mode was used for the first time for trains entering from on a track connecting from an old line. The section of line controlled by the
electronic signalling centre at Wurzen now makes reversible operations possible continuously from Leipzig-Engelsdorf to Bornitz and Leipzig Hauptbahnhof to Oschatz. €530 million had been invested in the upgrading of 51 km of lines by the beginning of 2002. With more than 220 trains per day, the line was considered to be the most important railway line in Saxony. During the
2002 European floods, two bridges to the east of Riesa collapsed and an embankment was severely damaged. The section was completely closed from 16 August 2002. Regular operations were resumed with two single-track temporary bridges on 31 October 2002. The second track at Röderau was put back into operation at the end of August 2003 The total damage to the track to the end of 2002 was estimated at €60 million. The Riesa–Zeithain section, including the three-track Elbe crossing, and the new selection of line connecting to the Berlin–Dresden railway were completed as part of the third stage of construction. The 13 km long upgrade of the line between Dresden-Neustadt and Coswig began in the autumn of 2009 and is expected to be completed in 2016. As a result of the upgrade, two separate tracks will be established for both the long-distance traffic and the
Dresden S-Bahn. The signalling and the S-Bahn stations along the line are being completely renewed and a new Dresden Bischofsplatz station is being built as part of this work. Once the work is completed, the speed limit on this section will increase for long-distance and regional traffic from 120 km/h to 160 km/h. Work has not begun on sections of this line at Riesa station and on the Röderau–Zeithain junction and Zeithain junction–Weißig sections. Between Weißig (km 77.9) and Coswig (km 101.3) the line was upgraded for the use of active tilting In July 2010, it was expected to be completed by the spring of 2016. Deutsche Bahn justified the delays compared to the original plan as being a result of the delays in the finalisation of the financing of all parts of the project until October 2009. The section between Dresden-Neustadt and Coswig is now expected (as of 2014) to be completed in 2016. The track has been equipped with ETCS Level 2. It is not known (as of summer 2015) when continuous operations at 200 km/h between Riesa and Coswig will be possible. Assuming sufficient federal funding, it was planned in mid-2008 that the line would be completed in 2014.
Cost From 2008 The European Union is contributing €50 million from the
European Regional Development Fund for the financing of construction phase 3. It is estimated that approximately €222 million will be spent on upgrading the Dresden-Neustadt–Coswig section, including almost €91 million for the upgrade of the S-Bahn.
Economic benefits and traffic A
cost-benefit analysis of the development project from April 2010 provided a cost-benefit ratio of 4.2. According to a statement of the
Verkehrsverbund Oberelbe (Upper Elbe Transport Association) in April 2014, about 7,200 passengers were counted on weekdays between Dresden and Riesa or
Großenhain and about 11,700 between Dresden and Radebeul. The volume of passengers increased by 6% between Dresden and Radebeul in 2011–2012. ==Route==