The roots of S-Bahn Mitteldeutschland go back to two separate S-Bahn networks in Halle and Leipzig, which were established separately in 1969 and then linked in 2004.
The Halle Network The Halle network used to connect the northern district of
Halle-Trotha in a U-shaped route through the
main train station with the residential suburb of
Halle-Neustadt on the western bank of the
Saale and then on to the last stop
Halle-Dölau. Meanwhile, the track section from Halle-Nietleben to Halle-Dölau has been abandoned.
The Leipzig Network The Leipzig route network started northward from the
main train station (a
terminal station) going around on both sides of the city and joining in the south in
Markkleeberg. This distinctive heart-shape was driven as a circular line in both directions, which ran to
Gaschwitz in the south. Later lines were built out to
Wurzen in the east and
Grünau in the West. On 29 February 1968, the Leipzig
Bezirk government decided to build an S-Bahn network. Already at the spring
trade fair, the "S-Bahn-style rapid transit" system was demonstrated between the
main station and the newly established
Messegelände (Exhibition Center) stop. By 12 July 1969, the S-Bahn network was expanded to the entire heart shape, in order to cope with traffic volume of the 5th East-German Gymnastics and Sports Festival (). The two branches were named S1 and S2. For the first two days the trains were free, which led to overcrowding. The fare then set absurdly high, with a single ride costing 50
Pfennig, a short distance ride up to five stations costing 30. Changing to transportation run by the
Leipziger Verkehrsbetriebe (LVB), or motorized transport required a new ticket, although combined monthly tickets were issued. In contrast, a single ride ticket in the city of Berlin (with transfer) only cost 20 Pfennig and the rides on the LVB could be as low as 16.7 Pfennig, with the use of multiple-ride cards.
Connecting both networks to Leipzig-Halle S-Bahn in 2004 Although dense suburban traffic between Leipzig and Halle had already existed for decades (from 1928, powered coaches and later series ET 41 ran on this route), a special tariff was never introduced on the line. On 19 March 2002, construction work began in Halle for the new commuter train route between the two cities. The commissioning of the 234-million-euro project was planned for December 2004. The construction costs were raised primarily by the German federal government (135 million euros) and the states of Saxony-Anhalt (39 million euro) and Saxony (34 million euro). The project was completed on schedule on 12 December 2004. In Leipzig, the route leads from the main station directly over the original route used for the decades only by freight trains of the Magdeburg-Leipzig Railway Company to
Leipzig-Wahren. The existing
RegionalBahn line 56 via
Wiederitzsch was replaced by the S-Bahn line. As a result, the travel time of 36 minutes is unchanged, despite five stops being added. Since the 5 December, the RB 56 route has been reactivated in a trial run with passengers. In addition, the
RegionalExpress line 5 trains took over the role of an "Express S-Bahn" which has run since 30 June 2003, in a special hourly service to the
Leipzig/Halle Airport. It was not necessary to introduce a special tariff because of the existence of the Mitteldeutschen Verkehrsverbundes since August 2001.
Routes until April 2011 In the times of the
German Democratic Republic, Leipzig had three lines designated A, B and C. These were later changed to S 1, S 2 and S 3. The S 2 line (known as the "Forest Railway") was shut down in 2002. The S 1 line was then in 2004 divided into the lines S 1 and S 2 so that the platform ramps in the tunnel do not have to cross unnecessarily often. •
S 1, formerly
A:
Leipzig Miltitzer Allee –
Leipzig-Plagwitz – Leipzig main station –
Markkleeberg–
Markkleeberg-Gaschwitz – Borna; since 2009
MRB 2. •
S 2, formerly
C ("Forest Railway"): Leipzig-Plagwitz – Markkleeberg-Gaschwitz •
S 3,
S 11, formerly
B to Wurzen; since 2009 the
MRB 11. In 2009, the operation of the line that runs eastwards from the
Leipzig main station was awarded to the
Mitteldeutsche Regiobahn thus effectively reducing the size of the S-Bahn network. On the routes concerned, the timetable did not change. Because of cost cutting, the remaining S 1 line between Leipzig Miltitzer Allee and
Leipzig Hauptbahnhof was cancelled on 30 April 2011. As a replacement, two bus routes and additional tram services are being offered by the LVB. The S 1 line was to be reopened with finishing the City-Tunnel Leipzig and opening the new S-Bahn Mitteldeutschland network in December 2013.
Routes May 2011 - December 2013 The S-Bahn Leipzig-Halle, which was operated by
DB Regio then, comprised the two lines, the S 7 and S 10. Trains run about every 30 minutes. The former lines S 2
Leipzig Hauptbahnhof – Borna (– Geithain) and S 11 Leipzig Hauptbahnhof – Wurzen (– Oschatz) had been operated since 2009 by
Mitteldeutsche Regiobahn (MRB) as lines MRB 2 resp. MRB 11 and were therefore not designated as S-Bahn routes any more. On weekend nights only, DB run a few services on the line 11 as S 11. ==Infrastructure==