Renovations to upgrade the facility began in May 2009 and were completed in spring 2012. Among the improvements are an expansion of , the addition of 18 luxury suites, improved concessions and washrooms, a new press box, and a restaurant/lounge overlooking the ice. The total budget for the building enhancement was $33.722 million and was to be shared by the City of Lethbridge, a Municipal Sustainability Initiative Grant, and a Major Community Facilities Grant. A $1,216,500 video scoreboard was installed and was funded by the City of Lethbridge, the
Lethbridge Hurricanes, and savings to the original project budget. ==References==