Plans to restore the Lichfield Canal were first raised in 1975, when area planning authorities were required to produce county structure plans. The
Inland Waterways Association (IWA) encouraged all members to ensure that local waterways were properly noted in the structure plans. Ideas for the restoration were put before the West Midlands planning team. Although the scheme was deemed to be unviable, interest in restoration continued, and the
Lichfield & Hatherton Canals Restoration Trust (LHCRT) was formed to promote the restoration of the Lichfield Canal and the
Hatherton Canal.
Lichfield District Council allowed the Trust to start work on a half-mile (0.8 km) section near Fosseway Lane in 1990. In 1993, the Trust published detailed plans for the Ogley Locks Branch, now formally branded the "Lichfield Canal". All of the canal are within the jurisdiction of Lichfield District Council. The Trust began working on three main sites, as they became available. The first site was the half mile at Fossway Lane, bounded by locks 18 and 19, which was owned by the council. The second was at Darnford Lane, on either side of lock 29, which was bought by the council in 1995, using a Derelict Land Grant. The third was at Tamworth Road, covering locks 24 to 26. The upper two have been largely restored, while lock 24 was excavated to assess its condition, but was filled in again to conserve it, pending a decision on how the canal would cross Cricket Lane, immediately upstream from the lock. This whole area was landscaped, and designated the Borrowcop Locks Canal Park. In 2023, the lock was re-excavated and turned into a narrows, by removing the gates and lowering the upstream cill. The pound immediatedly above the lock has been lowered, to enable it to pass under Cricket Lane, where a new bridge will be built by Persimmon Homes as part of a housing development. A new lock 24 will then be constructed upstream from the bridge. Restoration was threatened by the construction of the
M6 Toll motorway around the north of
Birmingham, which cut across the canal's route. The Inspector heading the enquiry for the Northern Relief Road ruled that the contractor would only be responsible for the footings for
a new aqueduct to carry the canal over the motorway, and that the Trust would need to raise the costs for the rest of the structure. An appeal was launched for funds, headed by the actor
David Suchet, and together with a grant of £250,000 from the Manifold Trust, the £450,000 cost was met, the road contractors built the supporting columns, and on 16 August 2003, a steel trough was craned into position, having been pre-fabricated by
Rowecord Engineering, who are based in South Wales. (The aqueduct has been finished but the canal has yet to reach it, giving it an odd appearance). This had a beneficial side-effect – the Government promised that never again would a new road be built in the path of a waterway restoration scheme, unless an aqueduct or tunnel was provided. A new bridge taking Cappers Lane over the canal near Whittington was opened by
David Suchet on 21 April 2006. Construction costs came from the
European Regional Development Fund, but the new bridge will be demolished as part of the
High Speed 2 rail link construction. It will be replaced by a new bridge further to the east, and the rail project will construct a diversion for the canal to enable Cappers Lane Viaduct to be built. By August 2010, most of the work on a by-wash for lock 25, adjacent to the Borrowcop Locks Canal Park, had been carried out by members of the Restoration Trust, with help from the
Waterway Recovery Group during weekend visits to Lichfield. The canal between Lock 25 and 26 was filled with water in April 2011, the first part of the canal to be filled with water since restoration works started. The end of the canal from Huddlesford Junction had been used for moorings by the Lichfield Cruising Club since 1959, and by 2006 included of moorings, a winding hole and a slipway. Recognising that the restoration of the canal would result in some of these moorings becoming unusable, the club purchased an adjacent field in 2006, on which to construct new moorings. Following over 10 years of negotiations, High Speed 2 agreed to construct the new moorings, as they needed some of the field for their own project. Work started in late 2021, and was completed in August 2022. In September 2025, the LHCRT received a £200,000
Community Infrastructure Levy grant from Lichfield District Council to support Phase 2 of the Gallows Reach section. The funding covers works on a 225-metre canal stretch, including sheet piling, lining, and the creation of a new pedestrian route connecting local housing developments. ==Route==