Hanoi Metro Line 3, also known as Line Nhổn - Ga Hà Nội, is a medium-capacity rapid transit service of the Hanoi Metro network, operated by Hanoi Metro Company. Colored dark red on transit maps, the line currently runs from Nhổn, a suburb in Bắc Từ Liêm District, west of city center, to its current terminus in Cầu Giấy Bus Interchange, located in Cầu Giấy district. When fully operational, the line will continue eastbound toward Hanoi Station, providing a direct connection to downtown Hanoi and the city's main railway station. The line operates between 5.30 am and 10pm, with headways of 6 minutes during peak hours, and 10 minutes during off-peak hours. All trains on Line 3 operate with a 4-cars formation.

History
Initial developments Line 3 dated back to 1998, when the Vietnamese government approved the 2020 vision Master Plan, which prioritise the building of a rail transit system, with a target to build 5 metro lines. Line 3 was one of the original lines considered in the master plan. Two separate preliminary feasibility studies was conducted in 2004 and 2005 with the help of the Asian Development Bank to determine the viability of Line 3. Four options were originally considered: • An elevated metro line running from Nhổn depot to Swedish Embassy on Kim Mã Avenue, then running underground to Hanoi Station; • An at-grade tramway section between Nhổn and Ringway 3, then an elevated line to Swedish Embassy on Kim Mã Avenue, then running underground to Hanoi Station; • Similar to option 2, but the at-grade tramway would be converted to a dedicated metro line; • An at-grade tramway section between Nhổn and to Swedish Embassy on Kim Mã Avenue, then running underground to Hanoi Station. Out of all options, options 2 and 3 were eliminated from further consideration due to congestion and performance issues associated with a mixed circulation tramway system. Option 4 was discounted from further consideration because even though it involved a system operating on a partially dedicated route, significant adverse changes to traffic management were required, particularly at intersections and pedestrian crossings and it would have resulted in reduced operating efficiencies and travel times. As a result, option 1, which was forecasted to carry up to 458,000 people daily, was selected as the preferred option. The name and location of stations were finalized in the 2009 Final Feasibility Study. Based on this study, fifteen stations were reduced to 12 stations, 8 elevated and 4 underground. A twin bored tunnel concept using tunnel boring machines (TBM) was selected to tunnel 15 to 8 m underground and to utilize the centerline of existing surface roads. Two underground stations, Cát Linh and Văn Miếu, were relocated one block eastward to avoid cultural significant sites. == Budget ==
Budget
Beside 276 million euros from the Hanoi city's budget, the project also receives 726 million euros from the four donors - the French government (DGT), French Development Agency (AFD), Asian Development Bank (ADB), and European Investment Bank (EIB). == Construction progress ==
Construction progress
Implementation of the project is delayed by four years compared to the original schedule with completion expected in 2021. As of March 2017, the project has achieved 30% physical progress over the elapsed project life of 9 years. However, the project completion is expected to be delayed to 2027. == Route ==
Route
Line 3: Nhổn - Hanoi Station section starts from Nhổn - to National Highway 32 - Cầu Diễn - Mai Dịch - Ring road 3 intersection - Cầu Giấy (ring road 2 intersection) - Kim Mã - Giang Vo - Cát Linh - Quốc Tử Giám and ends at Tran Hung Dao Street, in front of Hanoi Station. == Stations ==
Stations
Phase 1 The 1st phase of Line 3 has 12 stations including 8 elevated stations (Nhổn, Minh Khai, Phú Diễn, Cầu Diễn, Lê Đức Thọ, National University, Chùa Hà, Cầu Giấy) and 4 underground stations (Kim Mã, Cát Linh, Văn Miếu, Hanoi Station), with concourse level, elevators and lifts. The railway platform is long. File:Cau Giay Station 20230430-1.jpg|Cầu Giấy station File:Chua Ha Station 2022-06-13.jpg|Chùa Hà station File:レドゥクト駅の駅舎.jpg|Lê Đức Thọ station File:National University station of Line 3, Hanoi Metro, viewed from above.jpg|National University station File:Nhon station viewed from entrance.jpg|Nhổn Station Phase 2 The 2nd phase of Line 3 will have 7 more stations (Hàng Bài, Trần Thánh Tông, Kim Ngưu, Mai Động, Tân Mai, Tam Trinh, Yên Sở) all being completely underground with 1 depot located near Yên Sở Pumping Station. This section is 8786 m long (8.13 km underground, the remaining is for tunnel and on ground). == Fares ==
Fares
Beginning from Aug. 1st 2025, Line 3's fares are as follows: == See also ==