The scheme was initially designed by engineer
Charles Meik but after his death in 1923, the scheme's realisation was left to
William Halcrow, by then a partner in the firm founded by Meik's father
Thomas Meik. The project was finally sanctioned by Parliament in 1921, but construction did not start until 1924. Given the scale of construction, it was undertaken in three main phases: • The works to the west of Loch Treig, including the pressure tunnel, intake, powerhouse, and smelter. • The Treig and Laggan dams, plus connecting tunnel and intakes. • The Spey dam, Crunachdan cut and tunnel, plus the River Mashie diversion and Strathmashie tunnel. Over 3,000 men were employed during the peak of construction. A
narrow-gauge railway was used in construction and subsequent maintenance of phases 1 and 2, see
Lochaber Narrow Gauge Railway for details.
Stage 1 – downstream of Loch Treig The first stage of construction took five years, from 1924 to 1930, and cost around £3m. To facilitate construction, work progressed in both directions from 11 intermediate points: four vertical shafts and seven horizontal adits, giving a total of 23 working faces including the western portal above Fort William. These intermediate points were located close to watercourses, which were later captured by a series of dams and contributed around 16% of the total water for the scheme. The power station and smelter were completed by the end of 1929, initially equipped with five 6,800 kW generators, connected to Pelton turbines. The turbines sat in a deep rock excavation, as close to sea level as possible to maximise the head of the scheme. powered only by the waters from the side streams. Three years later, following a period of slack demand for aluminium, the power station was upgraded. Three additional pipes were installed on the hillside above the power station. These were in diameter, delivered in long sections, and welded together in-situ. Five additional Pelton turbines and generators were installed, each rated at 7,000 kW.
Treig Dam A dam was built approximately 1/4 mile (400 m) downstream of Loch Treig, raising the top water level by to
OD. This significantly increased the storage available, with 7,838 million cubic feet (221.9 million m3) available above the lowest draw-down level of OD. The dam also increased the head of the hydro scheme, providing more power. The dam is rock-filled with a central concrete core-wall keyed into the bedrock. The exposed part of the dam is high and wide, while the core wall has a crest length of and maximum depth of . Both upstream and downstream faces have a slope of 3:1, with the spillway protected by reinforced concrete, cast in-situ. In plan, the dam has a slight curve with a radius of , although it does not function as an
arched dam. The dam has a plain spillway along its length, together with six
siphons to increase the flood flow capacity. Many of these Canadian soldiers were ex-miners from
Kirkland Lake. Water impounded by the dam flows westwards through a cut into Loch Crunachdan, against the natural flow of water. It then passes through a tunnel approximately long which discharges into the eastern end of Loch Laggan. The maximum abstraction from the Spey is , although the average for 2020–2022 was just 14 m3/s. The tunnel was constructed in 1941, completed at the end of December. This was to replace the original twelve turbines, which were horizontal-axis twin-jet
Pelton wheel machines driving two
DC generators with a total capacity of 72 MW. Five new horizontal-axis
Francis turbines driving AC generators were installed by 2012, each rated at 17.3 MW giving a 20% increase in power output. ==Present operation==