The engineering service contract for design review, procurement and consultancy during construction of the dam was given to
SMEC Holdings of Australia. The contract was awarded to Sinohydro of China in January 2009, with completion planned for October 2011. In May 2010 the Minister of Minerals, Energy and Water Resources warned that the water pipes from the Lotsane Dam to the villages would cut across some ploughing fields belonging to Maunatlala and
Mokokwane residents, but said that the villagers would be compensated. In August 2011 the deadline for completion was extended to December 2011. As of February 2012 the dam was complete and starting to hold water, but did not yet have enough to start supplying the villages since there had not yet been any heavy rainfall in the catchment area. ==References==