Prior to the construction When the Dutch branch of Deloitte wanted a new headquarters, it chose the current location of the Maastoren. Both companies chose OVG as the developer of the new office building. Dam & Partners Architecten designed the Maastoren with
Odile Decq Benoit Cornette. Also, engineering firm Zonneveld and the company Techniplan Adviseurs were involved in the developing process.
Besix was the main contractor, and received €67 million for building the Maastoren. At the end of May, alderman
Hamit Karakus said to the council that the Maastoren would be built and that the municipality would listen to the objections. The council agreed with the construction in the following month. As a reaction,
Vereniging Woon- en Leefklimaat Kop van Zuid/ Noordereiland (Dutch for
Association Living Environment Kop van Zuid/Noordereiland) filed a lawsuit against the municipality of Rotterdam. The association aimed at preventing the Maastoren from being constructed, and was previously known as
Comité Maastoren Nee! (Dutch for
Committee Maastoren No!). 200 objections against a license had been filed, mostly because of the height of the Maastoren and the above ground parking garage.
Construction The process of making the site ready for construction started at the end of July 2006, but the preparations were shut down two weeks later on 3 September. On 21 September, the preparations were continued. The digging of the
foundation started the following month. Part of the construction site was kept dry using
sheet piles, because that part was situated in the river. In November 2006, all the remaining objections against the Maastoren were rejected by the general committee on objections of Rotterdam. The lawsuit against the construction, however, was still ongoing. On 25 April 2007, the
groundbreaking took place.
Ivo Opstelten, who was mayor of Rotterdam at that time, hammered the first pile into the ground. Back then, the opening of the Maastoren was planned in 2009. Meanwhile, the judge had given the verdict in the lawsuit of the association against Rotterdam, that was filed to stop the construction. The judge said the license was justified, and thus the municipality had won the lawsuit. On 27 May 2009, the Maastoren was topped out. At that time, all floors up to the twentieth floor were completely finished. To celebrate this occasion, alderman Hamit Karakus and CEO of OVG Coen van Oostram
abseiled down the building to the 31st floor two days later. The construction was completed in November 2009.
Opening and sale The Maastoren was put into use on 15 March 2010, and was officially opened two months later on 28 May. OVG, the developer, received a plaque from the
Council on Tall Buildings and Urban Habitat. The plaque states the Maastoren has a height of , and is the tallest building in the Netherlands. The plaque is displayed in the lobby of the Maastoren since the opening. During the opening,
Ahmed Aboutaleb, the mayor of Rotterdam, received a copy of the book
Maastoren about the building, which was published by the Rotterdam Skyscraper Foundation. In December 2014, the American real estate company NorthStar bought a portfolio, that consisted of eleven office buildings including the Maastoren, from SEB Asset Management. NorthStar paid €1.1 billion for the entire portfolio. == Architecture ==