In 1963, a report by US consultancy firm De Leuw Cather and Co recommended that a motorway and rapid public transport system be developed for Auckland. This included the
Southwestern Motorway, a link between the proposed
Northwestern and
Southern sections that would bypass the city centre, and would involve a large-scale motorway crossing of the Māngere Inlet adjacent to the Old Māngere Bridge. The first section of the Southwestern Motorway, the Onehunga Bypass, was completed in 1977, spanning Queenstown Road in
Hillsborough and terminating at the Old Māngere Bridge. Two contracts were let for the construction of the motorway bridge: one to Gilberd Hadfield Pile Co Ltd to construct the foundations, signed on 25 January 1973, and a second for the construction of the bridge structure, awarded to the Wilkins & Davies Development Company Ltd and signed on 24 July 1974. The contract with Wilkins & Davies Development Company was suspended in July 1978, and a new contract with
Fletcher Construction was awarded in November 1980 to finish construction. In September 2007,
Auckland Regional Transport Authority proposed to pledge NZ$2.5 million for future-proofing works to ensure that a rail link would be included. The design envisaged the future railway line run on the new bridge piers for part of the distance underneath the motorway structure, thus saving some of the high costs associated with strengthening the bridge to be able to take a
cantilevered bridge – estimated at around NZ$20 million in extra costs.
Interchange issues In July 2007, Auckland City Council commissioners gave approval to widening the approach motorway for the bridge through
Onehunga Bay, but opposed the new interchange design north of the bridge favoured by Transit, which intended to construct it around 7 m high over Gloucester Park and the Hopua volcanic tuff ring. The council's preferred version was to build the interchange at ground level with part of the motorway in a
cut and cover tunnel. Partly due to this, Transit New Zealand decided in August 2007 to continue with building the new bridge without including a new interchange for the time being.
Design Transit New Zealand made provision for a future rail link under both bridges to connect to Auckland Airport, The bridge has 7 piers with a total of 14 columns, and consists of approximately 10,000 cubic metres of reinforced concrete (with the rebar weighing approximately 1,000 tons). Some of the piles were driven 50m deep, to avoid issues with the softer top layers in the Manukau Harbour. The bridge itself consists of single-pour concrete columns and form traveller-constructed balanced cantilever decks. Existing pedestrian and cyclist links on the old 1914 bridge closed to motor vehicles were retained and are connected to a shared path along the Mangere Bridge waterfront reserve via a new walking/cycling bridge over Onehunga Harbour Road – linking Onehunga to Mangere Bridge suburb and to the
Waikaraka Cycleway.
Ancillary works A number of works related to
environmental mitigation, post-project landscaping or improvement of non-motorway transport links were associated with the project (and either paid for or undertaken by NZTA). These included a 3.5m wide replacement foot/cycle bridge over Beachcroft Road, a new 3.5m wide foot/cycle bridge over Onehunga Harbour Road at the Old Mangere Bridge, an upgraded underpass under the motorway connecting to Onehunga, as well as improved links to the
walking and cycling paths along the harbour and motorway edges and improvement works on the Old Mangere Bridge causeway. After finishing work, NZTA reinstated their large construction staging site along the southern harbour front as an open space, "passive recreation" park with Pohutukawa. ==See also==