The Metrol train control complex was built as part of the
City Loop project of the 1970s. The original site was on
Batman Avenue, beside the
Jolimont Yard, and adjacent to Electrol, the control centre for the railway
electrical substations and
traction power supply. During construction, it was revealed that the Metrol building would block the view from
Russell Street to the
Botanic Gardens and
Government House, and that no planning permit had been applied for. Bill Gibbs, chairman of
VicRail, stated that under Section 79 of the
Railways Act 1958, VicRail had the right to build anything on its own land that it deemed necessary. The
City of Melbourne and the
Board of Works asserted that a permit
was necessary, because the building was within 60 metres of the
Yarra River.
State Premier Rupert Hamer responded to the public outcry by ordering the half-constructed building to be demolished. He also told all government departments that they must apply for planning permits, whether they were legally obliged to or not. As part of the removal of Jolimont Yard, the Metrol building was demolished in 1999, and Metrol operations were moved to Transport House (589
Collins Street, Melbourne). The functions of Electrol were relocated to a permanent location elsewhere. The Transport House location was only intended to be temporary, pending the replacement of the elderly technology with a new system; however, as of July 2017 Metrol was still at the same location (now named 595 Collins Street). When
M>Train was franchised to operate half of the Melbourne suburban network, after the
privatisation of the system, the company was required, under its contractual obligations, to complete a new Metrol system that was originally contracted by the PTC that was previously required to be complete by 1999 to allow the relocation before Privatisation. Due to mismanagement by Adranz and the PTC the contract was extended to June 2001 and therefore wsa required to be completed by M>Train. Work on the Train Management Facility started when
Bombardier Transportation was awarded an $11 million contract, with completion originally due in 1999 but extended until mid-2001. The project included plans for a back-up "disaster recovery centre" at
Melbourne Central station. In 2003 the State Government and M.Train agreed to cancel the $18 million contract owing to the undeliverability of the original PTC specification; however publicly, saying it was unhappy with the deal. On 28 June 2005, a leak in an air-conditioning hose caused Metrol to be shut down for two hours from 11.40am, causing 30,000 passengers to be stranded and 66 trains cancelled, with 23 more trains cancelled later in the day due to flow-on effects. Train operator
Connex Melbourne was fined $300,000 by the State Government for failing performance benchmarks. The first stage was a $27 million contract, awarded to
Westinghouse Rail Systems in March 2007, for the design and installation of the new Train Control and Monitoring System. A customised version of the SystematICS control system was to be provided, with completion expected in November 2010. At a later date, separate contracts were to be offered for a new passenger information system, a new reporting system, and a refurbishment of the central control facility. ==References==