The Mombasa–Nairobi Expressway or Nairobi–Mombasa Expressway, also known as the Nairobi–Mombasa Highway, is a proposed four-lane toll highway in Kenya. The highway will link Nairobi, the capital and largest city of Kenya to Mombasa, the largest seaport of the country. The new highway is expected to cut travel times between the two cities from the current 6 to 10 hours to approximately four hours.

Location
The road starts at Gitaru along the Nairobi–Nakuru Highway, approximately , northwest of Nairobi City centre. It continues in a general southeasterly direction, through Ngong, Ongata Rongai, Kisaju and Isinya to rejoin the existing Nairobi–Mombasa Road, just north of Konza. The highway passes through nine Kenya counties to end in the city of Mombasa at the Changamwe Roundabout, a total distance of about . The coordinates of this road at Kibwezi are: 02°25'04.0"S, 37°57'39.0"E (Latitude:-2.417778; Longitude:37.960833). ==Overview==
Overview
The planned expressway is a dual-carriage motorway with initially four lanes, expandable to six lanes in the future. The road will be capable of supporting sustained traffic speeds of up to per hour and will have controlled access. ==History==
History
In February 2015, the Kenyan government hired PwC to conduct a feasibility study on the commercial and technical viability of the Nairobi–Mombasa Expressway. The PwC report indicated the highway was viable if the highway operator collected a toll that would be used to retire the private capital used to develop the expressway. Starting about that time as well, the government of Kenya, through the Kenya National Highways Authority (KeNHA), began detailed talks with Bechtel International on a public-private partnership (PPP) to design, fund, construct and operate the highway. ==Construction costs==
Construction costs
The cost of constructing this expressway is budgeted at US$2.1 billion. ==Timetable==
Timetable
In August 2017, KeNHA signed a binding agreement with Betchel International, an American civil engineering and construction company to design, construct, and operate the proposed expressway. Completion of the first section was expected in October 2019, and the entire expressway was expected to open in 2024. In April 2019, the Business Daily newspaper reported that construction was expected to start in the second half of calendar year 2019. ==Developments==
Developments
In May 2024, president William Ruto, while on a state visit to the United States, witnessed the signing of an agreement between Kenya National Highways Authority (KeNHA) and Everstrong Capital the "United States infrastructure investment manager", to build this expressway at a budgeted price of US$3.6 billion. Funding is expected to be sourced from "pension funds, international investors, development agencies and Kenyan private investors". ==See also==