Transmission system More than 420
transmission substations in the Peninsular Malaysia, with a total installed capacity of 105,305 MVA, are linked together by approximately 21,000 circuit-kilometers of overhead lines and underground cables operating at 132, 275 and 500
kilovolts (kV). The 500 kV transmission system is the single largest transmission system to be ever developed in Malaysia. Begun in 1994, Phase 1 involved the design and construction of the 500kV overhead lines from
Gurun, Kedah in the North along the west coast to
Kapar, in the central region and from
Pasir Gudang to
Yong Peng in the south of Peninsular Malaysia. The total distance covered for the 500 kV transmission lines is 784 circuit-km and the 275 kV portion is 9,257 circuit-km as of February 2017. To cater for the new plant up of generators, namely 3,100 MW Janamanjung Power Plant in the west coast, 372 MW Ulu Jelai Hydro Electric Power Plant in the east coast, and 4,100 MW Tanjung Bin Power Plant in the south, the 500 kV transmission system was extended from Bukit Tarek to Yong Peng via interconnection allows for electricity of Ayer Tawar, Tapah, Bentong South and Lenggeng. The completion of this interconnection allows for electricity transmission to the load centre, which is located in the Klang Valley area of Peninsular Malaysia. A project involving laying a 730 km high-voltage direct current transmission line and a 670 km undersea cable for the 2,400-megawatt
Bakun hydroelectric dam was considered. This would have connected all three of Malaysia's electric utility companies with state grids:
Tenaga Nasional Berhad (TNB),
Sarawak Energy Berhad (SEB) and
Sabah Electricity Sdn Bhd (SESB). Many of Sabah and Sarawak's generation plants are still not interconnected to a grid.
Type of National Grid's transmission system Connection to Thailand The National Grid is interconnected in the north to
Electricity Generating Authority of Thailand (EGAT)'s transmission system via the 300 kV HVDC interconnection of 300MW capacity and 132 kV HVAC double circuit overhead line of 90MW capacity each, linking
Bukit Ketri-Chuping in the state of
Perlis with
Sadao, Sadao in
Thailand.
Connection to Singapore In the South of Malaysia, the National Grid is connected to the transmission system of
Singapore Power Limited (SP) at
Senoko via two 230 kV
submarine cables with a transmission capacity of 200 MW each.
Power generation Power generation capacity connected to the Malaysian National Grid is 22,858
megawatt, with a maximum demand of 17,788 megawatt as of April 2016 according to Suruhanjaya Tenaga. The generation fuel mix in peninsular is 45.55% gas, 50.23% coal, 3.59% hydro and 0.63% from other forms of fuel.
Distribution level Distribution lines of 66kV, 33 kV, 22 kV, 11 kV, 6.6 kV and 400/230 volt
electricity distribution network connect to the National Grid via transmission substations will have their voltages stepped down by
transformers. == Major incidents ==