At the end of 2014, the Ministry of Sport of the Russian Federation signed a contract with OAO Stroytransgaz for the construction of a stadium worth 16.756 billion rubles for an area of 21.6 hectares. The total estimated cost of the stadium, which includes, in addition to the construction and installation works performed by the general contractor, also the design cost, is 17.9 billion rubles. The area of the stadium borders on the area of historical buildings, where the architectural monument
Alexander Nevsky Cathedral is located, too. In 2016, the basic concrete works were completed - all the floors of the stadium and the platform of the upper tier were erected. The builders began to install engineering systems. By the end of 2016, the contractor had installed metal structures above the tribune zone, including the support ring - just over 50% of the stadium's total coverage. In 2017 completion of installation in the final design position of steel structures of the coating, concreting the stands of the lower tier and pedestrian overpass. Also, the builders are to carry out the installation of the roof, the facade, the construction of the football field, and complete the finishing work. Under the terms of the contract, construction and installation work is expected to be completed in December 2017. ==Transportation==