Apr 2005: The project is announced by the then Prime Minister of India
Manmohan Singh. •
Oct 2006: The Dedicated Freight Corridor Corporation of India (DFCCIL) is formed by the
Ministry of Railways on 30 October. •
Feb 2008: The Cabinet Committee on Economic Affairs (CCEA) approves the Western DFC and the Eastern DFC. •
Sep 2009: The Union Cabinet approved a
JICA loan. •
2018-19: DFC is revived by the Union government after a decade of inactivity, with a target of going live by March 2023. However, the COVID crisis stalls the project's progress, and the timelines are shifted by a year. A major part of the project becomes operational by 2023. •
Jun 2023: 77% of the DFC is completed and the project is set to be completed by the end of 2023. •
Oct 2023: The last leg of the Eastern DFC underwent a successful trial run. With this, the line is completed to
Son Nagar. •
Feb 2024: Construction has been completed. •
Apr 2024: Fully operational'''''' ==See also==