The cutter was originally proposed to replace aging medium endurance cutters with more capable and technologically advanced cutters as a part of the
Integrated Deepwater System Program. By 2010 and 2011 some commentators speculated that the entire program was vulnerable to cancellation on budgetary grounds, because of the long delay in finalizing a preliminary design. A bill passed by the
United States Congress in November 2011, imposed conditions on the USCG's capital expenditures, that revolved around the design of the Offshore Patrol Cutter, granting greater certainty to the project. By December 2011 plans for the cutter started to become more concrete. Plans to include a
stern launching ramp, as on the
National Security Cutters and the
Fast Response Cutters, had been eliminated on budgetary grounds. In February 2014, the USCG announced that
Bollinger Shipyards,
Eastern Shipbuilding, and
General Dynamics Bath Iron Works had been awarded design contracts for the OPC. The
Government Accountability Office denied contract appeals by VT Halter Marine and Ingalls Shipbuilding. In September 2016, Eastern Shipbuilding of Panama City, Florida, was awarded a $110.3 million contract to build the first Offshore Patrol Cutter with an option to purchase eight additional cutters. In October 2016 the Coast Guard issued a notice to proceed with the detailed design of the Offshore Patrol Cutter to Eastern Shipbuilding. The first Offshore Patrol Cutter was originally expected to be delivered in late 2022. In total, the 25-ship deal could be worth up to $10.5 billion, according to 2012 Coast Guard estimates. In July 2017, Eastern Shipbuilding completed its Initial Critical Design Review for the Offshore Patrol Cutter. This leads to the Final Critical Design Review for the Offshore Patrol Cutter. In August 2017, it was announced that the OPC's will be named "Heritage class" and the first 11 OPCs were named. The Heritage-class OPCs are named after cutters that played a significant role in the Coast Guard's history. In September 2017, the USCG exercised a fixed-price option to procure long lead time materials for the first Heritage-class cutter. The total value was $41.68 million and covered various materials and parts needed for the engines, switchboards and generators, steering and propeller components, and control systems. This included meeting Coast Guard requirements and meeting all American Bureau of Shipping Naval Vessel Rules. It is the first US Coast Guard cutter ever constructed to meet these very specific requirements. The construction of the first cutter, , was planned to begin in the late summer of 2018, with delivery in August 2021. In September 2018, the USCG exercised the contract option to begin construction of the lead Offshore Patrol Cutter, along with long-lead materials for OPC #2. The total value of the options exercised is $317.5 million. Delayed by the impact of
Hurricane Michael in October 2018, steel cutting for USCGC
Argus began in January 2019. In October 2019, the Department of Homeland Security approved a limited extraordinary relief for the offshore patrol cutter contract, as a result of damage to Eastern Shipbuilding facilities caused by Hurricane Michael and adjusted the offshore patrol cutter detail design and construction contract with Eastern Shipbuilding group for up to the first four hulls, providing $659M in additional funding. The Coast Guard will release a Request for Information to see industry interest in re-competing the remainder of the offshore patrol cutter
Program of Record. In July 2022, Austal USA was awarded the contract for detail design and material acquisition for the fifth hull in the class, with an option for up to 11 hulls in total (hulls 5–15). On October 7, 2023, first-in-class
USCGC Argus was launched by Eastern Shipbuilding. As of September 2025, the
Argus is still fitting out, and is not expected to be delivered until 2026. On March 5, 2025, Congressman Mike Ezell, Chairman of the Coast Guard and Maritime Transportation subcommittee of the House Committee on Transportation and Infrastructure, reported that the Coast Guard now expects delivery of the first Offshore Patrol Cutter, USCGC
Argus (WMSM-915), at the end of 2025, "four years late, and with a host of non-compliant parts." On June 7, 2025, a temporary stop-work order was issued on the third and fourth hulls of the class, both at Eastern Shipbuilding. The order did not effect hulls planned at Austal USA. On July 11, 2025, the stop-work order was expanded to an outright cancellation of the third and fourth hulls. The Department of Homeland Security announcement of the cancellation remarked in passing that
Argus was not expected to be delivered until the end of 2026 at the earliest. ==Ship list==