under construction in February 2023 The Alternatives Analysis yielded two LRT (
light rail) build alternatives, plus the required "No Build" and "TSM" (
Transportation System Management) options. A third LRT build alternative was added in February 2010, at the request of Little Tokyo stakeholders (including property, business, and homeowners). The operational intent of the project was to allow through running of service between the four corridors (Blue Line corridor, Expo corridor, Gold Pasadena corridor, and Gold Eastside corridor). All three build alternatives began at
7th St/Metro Center station, which was previously the northern terminus of the
Blue Line and the eastern terminus of the
Expo Line, which opened on April 28, 2012. All three build alternatives connected to the preexisting
Gold Line at
Alameda Street near
Temple Street or 1st Street. On October 28, 2010, the LACMTA Board of Directors opted for a fully underground option, rejecting at-grade and underground emphasis alternatives. This route remains underground below Flower and 2nd Streets until northwest of 1st/Alameda. By that point, the route would have split into two branches. Each branch would then emerge from a tunnel – one heading north to Union Station, the other east to the Eastside. Metro added this alignment in February 2010, after receiving public input on the other two options. This option puts the connector underground beneath 1st/Alameda. The fourth new station (at 1st/Alameda southwest block) would replace the existing
Little Tokyo/Arts District station. The third station (nearest the
Civic Center) was shifted slightly west toward
Broadway, to take advantage of redevelopment efforts in the historic core. This option is generally fastest and has fewest impacts during operations, but it would have more construction impacts and higher costs.
Comparison of alternatives The following table summarizes key characteristics of each alternative: In October 2010, Metro staff reaffirmed this recommendation, but with the 5th/Flower station removed. The report cited concerns for the overall project cost and the proposed station's short distance from Metro Center/7th Street Station, a mere three blocks, which might not have met FTA funding standards. However, proponents of a 5th/Flower station cited the high density of very large high-rise office buildings within one block of a 5th/Flower station and that such a station would relieve what is expected to be extreme pressure at Metro Center/7th Street (already experiencing pressure) once the E Line, then the Regional Connector are complete. At the Metro Board meeting in late October 2010, the Board certified the Draft EIS/EIR and accepted the staff recommendation of Fully Underground Alternative with the 5th/Flower station deleted as the Locally Preferred Alternative (LPA). The project staff will now conduct a final study of the LPA, which will culminate in a Final Environmental Impact Study/Environmental Impact Report (Final EIS/EIR). ==Project funding==