Timeline • 27 October 2017 – Construction as part of
Ballarat Line Upgrade commences. • 3 November 2017 – New station at Toolern (now
Cobblebank), on Melton Line, announced. • 20 December 2017 –
Wendouree Station upgrade announced. • 14 March 2018 – Geotechnical investigations begin to be carried out on the
Gippsland Line. • 19 July 2018 –
Ballan station upgrade plans revealed. • 22 October 2018 -Construction commences on
Shepparton Station stabling facility. • 30 May 2019 – Construction begins as part of
Donnybrook Station and
Wallan Station upgrades. • Early July 2019 – Total work time as a part of the
Ballarat Line Upgrade hits 1,000,000 hours. • 26 August 2019 – Construction at
Rockbank Station finishes, and the station is opened up to the public. • 20 November 2019 – Construction of the new
Avon River railbridge in Stratford commences. • 1 December 2019– New station at Toolern, named
Cobblebank, opens to public. • 6 December 2019 – Construction begins on stabling facility at Ararat. • 28 January 2020 – Construction begins on the upgrade of four level crossings on the
Warrnambool Line. • 23 April 2020 –
Donnybrook Station Upgrade completed, with addition of 150 new car parking spaces, new platform shelters and the city bound platform extended, improved pedestrian access, improved security with CCTV and lighting on platforms and in the car park. • 24 April 2020 – Works completed on four new level crossing boom gates along the
Warrnambool Line. • 31 July 2020 – 3 new stations, named
Huntly,
Goornong, and
Raywood, announced to be constructed on the
Bendigo railway line, to be completed by 2022. • 12 December 2021 – Construction at
Goornong Station finishes, and the station opens to the public. • 31 May 2022 -
Waurn Ponds Station upgrade completed, with addition of a second platform, an upgraded car park and a new pedestrian overpass. • 16 July 2022 – Construction at
Huntly Station finishes, and the station opens to the public. • 17 July 2022 – Construction at
Raywood Station finishes, and the station opens to the public. • 13 May 2023 - Construction of the new Waurn Ponds stabling facility finishes, allowing an additional 31 services per week on the
Geelong Line. • 26 August 2024 - Duplication of the Geelong line between Waurn Ponds and South Geelong completed, with second platforms at Marshall and South Geelong stations. The level crossings at Fyans Street and Surf Coast Highway were also removed and replaced with rail bridges. ==See also==