The River Till drains an area of Lincolnshire bounded by
Gainsborough in the north-west and
Lincoln in the south-east, where it joins the
River Witham at
Brayford Pool. The river is enclosed by earth embankments on both sides of the channel, to increase its capacity and to prevent flood water from inundating the surrounding land. These stretch from Stow Road Bridge to its junction with the Foss Dyke. Lincolnshire suffered severe flooding in 1795, when the
River Trent breached its bank at
Spalford, inundating some between the Trent and Lincoln, including swamp land at Broxholme and land at Saxilby where gorse and ling were grown. Lincoln High Street acted as a dam, penning the water to the west of the city, where water levels on the Foss Dyke were some above normal levels, and the flood water remained there for nearly three weeks. Following the disaster, an
Act of Parliament was obtained on 20 July 1804, which created two drainage boards, the Lincoln West (North District) board being responsible for some straddling the Foss Dyke and the River Till, while the Lincoln West (South District) board had responsibility for bordering the upper Witham. The boards were required to embank and drain the lands. The banks of the Till were extended during the 20th century, although below Tillbridge most were in place by 1886, when the first Ordnance Survey maps of the area were published. Water from land to the south of the Till drained into the Sincil Dyke through a tunnel under the River Witham. In order to drain land to the north more effectively, the Commissioners of the North District were authorised to construct a cast-iron tunnel under the Foss Dyke at Bishop Bridge, and a section of main drain which would link it to the main drain for the South District. In addition, they were to build a
catchwater drain at a higher level, to intercept run-off from the high grounds, which empties into the Foss Dyke at Bishop Bridge. By the time the work was completed, together with other work in the South District, the drainage scheme was more or less as it exists today. Many of the drains were protected by sluice doors, which were operated either automatically or manually, but before 1930, some water was pumped from the land at Broxholme and Saxilby with the pumps being maintained by the Church Commissioners or private landowners. However, during flood events, levels in the main drains rose rapidly, and the pumps could often not be used when they were needed most. With the passing of the
Land Drainage Act 1930, responsibilities were rationalised, with the Witham and Steeping Rivers
Catchment Board having overall responsibility, and the Upper Witham
Internal Drainage Board being constituted to manage the land drainage functions from 1 April 1933. The North District and South District Boards were abolished, and the Catchment Board took over the functions of the Lincolnshire and Nottinghamshire Commissioners of Sewers. Subsequent legislation resulted in the Catchment Board being replaced by the Lincolnshire
River Board in 1950, the Lincolnshire
River Authority in 1965, the
Anglian Water Authority in 1973, the
National Rivers Authority in 1989 and finally the
Environment Agency from 1996. Some 20,000 people live in regions of Lincoln that are susceptible to flooding. Most of the city's industrial buildings and around half of the commercial property is also at a high risk from flooding. There were major floods in the city in 1947 and 1958, and the amount of water delivered to the city by the River Till was a significant factor in the 1958 floods. Following these events, feasibility studies were carried out in 1977 to identify ways to mitigate flooding in the city. This resulted in the construction of two
washlands, one where the
River Brant joins the River Witham, to the south of Lincoln, and the other on the River Till, to the north-west. Work began in 1984, and the two schemes can hold back of floodwater. In both cases, a shallow embankment was constructed across the river valley, and the river passes through a control sluice, which can be used to limit the volume of water travelling downstream. Inlet and outlet sluices in the embankments can be opened to allow the water to flood the Till washlands, rather than allowing river levels in the city to breach the defences. The water from the washlands is subsequently released as levels through the city return to normal. Draining of the washlands is assisted by pumping stations, and the scheme was completed in 1991. The washlands were tested for the first time in 2000, when there was some local flooding of rural areas, and the storage of water prevented significant damage occurring in Lincoln. Much more serious was a flood event in the summer of 2007, which was caused by intense rainfall, and the flood defences worked as planned, with the River Till reservoir reaching 85 per cent full before water levels began to subside. The washlands were again partially filled in January 2008. A study carried out in 2010 noted that the Catchment Flood Management Plan for the Lincoln area recommends that the capacity of the washlands should be increased, to cope with the possible effects of climate change. ==Water quality==