The mechanical part Running gear The running gear consisted of three drive-axles mounted in the locomotive frame. The center drive-axle had a side-play of 2× . The two idle-axles were mounted in
Bissel trucks which were fixed to the frame. Those axles had a side-play of 2× .
Transmission of tractive force The tractive force was transmitted from the drive-axles to the frame. From there the force was carried over to the
towing hook and the buffers.
Drive The two motors were mounted in half height in the locomotive frame. Those two motors drove big cogwheels over
sprockets spring-loaded on both sides. Each of those big cogwheels drove a
jackshaft. The two jackshafts drove a shared slit coupling rod which drove – over a vertical
crosshead – the
crank pin of the center drive-axle.
Side rods connected to the slit coupling rod transmitted the force to the outer drive-wheels. This drive concept was later used by the
Ae 3/6II.
Locomotive body The locomotive body consisted of a frame built up with thick steel plates. On this frame the body was mounted with a cab at each end. The
towing hook and the buffers were fixed to an
abutment beam which was mounted to the frame.
The electrical part Primary circuit The electrical part was – in its arrangement – taken over from the
Be 5/7 of the
BLS. It consisted of a
diamond-shaped pantograph, a circuit breaker for isolating the respective pantograph,
lightning protection inductor and one more circuit breaker for isolating one half of the locomotive. All those components were mounted on the roof. The oil operated main switch was located in the locomotive body. The locomotive driver operated the switch via electric valves located in both cabs. It was also possible to operate the switch mechanically using a rod system. Finally it was possible to operate the main switch directly by using a
wrench. The two transformers were – unusually for the SBB – air ventilated. The design was the same as the
Be 5/7 of the BLS. The switches were fixed to the transformers. The connection to the respective voltage steps was executed with contact
camshafts. The switching process was started with special spark-extinguishing
camshafts. The step switch used compressed air and had 12 steps. Since the two switches were operated alternatively, this meant that 23 steps were required which meant that the switching time was very slow. To operate the step switches, the locomotive driver had to turn a vertical crank handle once for each step. It was possible to shut off power by running down both step switches with a special handle. The electropneumatical reverse switches were attached on the motors. A group switch was mounted by them which had to execute the following actions in case of a failure: • Separation of one transformer with its respective motor → Full speed, but only half tractive force • Separation of one transformer and feeding the two motors from the other one → Only half speed, but full tractive force In 1929 the delicate step switches were replaced by two hopper switches. The old controllers were at the same time exchanged to normal controllers with horizontal hand wheels.
Auxiliary systems The locomotive consisted of the following 100 V operated auxiliary systems: • two compressors • three fan groups (two for the transformers and one for the engine rooming) •
Motor-generator for charging the batteries for control power and lighting • cab heating The two old compressors were upgraded later to a modern MFO-compressor, which ran with the later auxiliary systems voltage of 220 V. The train heating system was fed over a separate oil propulsed main switch with 1000 V. This installation was later replaced by a separate heating transformer. The oil powered main switch was replaced by a heating hopper.
Electrical brake The SBB requirement requested an
electrical brake. This brake was shown in the blueprints but only in dashed lines and therefore not mounted in the locomotive. This brake was never upgraded because this "stopgap" locomotive was never used for services on the Gotthard railway line.
Multiple-unit control The locomotive was equipped with
multiple-unit control. The idea behind this was to lead a 425 t-train on the adjacent lines with low gradient using a Be 4/6 and then boosting it up for the steep gradients at the gotthard railway line using a Be 3/5. The idea of operating the train with one locomotive driver on the leading locomotive was definitely plausible. But the problem was, that for driving back the locomotive to the starting point another locomotive driver was needed. It is unknown if the multiple-unit control ever was tested. == Operational history ==