Fair Isle In January 2023, £26.7 million was awarded by the
UK Government, as part of the '
levelling up' fund, to the Shetland Islands Council for the purchase of a new ro-ro ferry for
Fair Isle and new terminals at both the
Grutness and
Fair Isle ports, including linkspans. The new ferry is expected to be similar to the
MV Snolda, with 25m length and capacity for about 4 cars and a crane. The work is due to be completed by April 2026. Works began at Grutness pier to facilitate this new vessel on 30 April 2025, with all Fair Isle sailings going to
Lerwick until they are completed. The contract was awarded to
Parkol Marine Engineering,
Whitby,
Yorkshire on 10 June 2025, with an expected delivery date of October 2026. The vessel will be a faster and bigger monohull that will have additional lift on capability and ability to operate to the current linkspans. The design, which was done by Chartwell Marine, was presented on the news in September 2025, for delivery end of 2026. The first steel was cut for the ferry, to be named
Good Shepherd V, on 13 November 2025.
New relief vessel On 13 February 2025, the council revealed that they are looking into building a new vessel, which would possibly replace or operate alongside the current relief vessel,
MV Fivla. This came after the Scottish Government gave the council £10 million funding for island connectivity, which will be used for this project. They put a due date for end of 2028, at which point the oldest vessel in the fleet will be 46 years old. Maritime unions and locals have expressed concerns over this fact due to ferries normally only having a lifespan of 25 years and half the fleet having a
grandfather clause allowing them to have passenger accommodation below the
waterline, making it inaccessible to many people. The council later came with a second option to make a vessel similar to MV
Linga, which would operate alongside her at
Whalsay, with
MV Hendra then becoming a second spare vessel. The tender for the new 33m max 500
GT relief vessel, designed by MacDuff ship design, went out on 29 January 2026. Delivery of the ferry is expected to be between 31 October 2028 and 31 March 2029. The full cost of the project is estimated to be £35.1 million. There is an option for two additional ferries however that is not being tendered at the moment.
Papa Stour (cancelled) There is also a project involving Coastal Workboats and BK Marine to trial a fully electric ro-ro ferry between
West Burrafirth and
Papa Stour. The cost of project will be roughly £9 million, with £6 million of which funded by the UK Government's Clean Maritime Demonstration Competition. This trial is due to last 4 weeks from March 2025, in hope of it taking full time service, where it would take over from the regular vessel,
MV Snolda, for the trial period. In April 2025, it was announced that the project will no longer take place on the Papa Stour route. The island community previously presented their concerns for the project going ahead with little to no consultation. == Previous Fleet ==