Shortly after the opening of the first railway in Switzerland, each region began to favour a separate north–south link through the Alps towards Italy. Eastern Switzerland supported a line through the
Splügen Pass or the
Lukmanier Pass, Central Switzerland and
Zürich favoured the
Gotthard Pass and Western Switzerland supported the
Simplon route. In 1871, the first line through the Alps was completed, connecting Italy and France by means of the
Fréjus Rail Tunnel. The
Compagnie de la Ligne d'Italie was founded in 1856 to build a connection between
Romandy and Italy through the
Canton of Valais and the
Simplon. On 1 June 1874, it was taken over by the
Simplon Company (
French:
Compagnie du Simplon, S), which was created to promote the project. This merged in 1881 with the company
Western Swiss Railways (French:
Chemins de Fer de la Suisse Occidentale, SO) to create the
Western Switzerland–Simplon Company (French:
Compagnie de la Suisse Occidentale et du Simplon, SOS). The French financiers of the SOS were able to secure financing for the tunnel in 1886. The company considered 31 proposals and selected one that involved the construction of a tunnel from Glis to Gondo, which would have been fully in Switzerland. From Gondo it would have continued on a ramp through the Divedro valley down to
Domodossola. At a Swiss-Italian conference held in July 1889, it was agreed, however, to build a nearly base tunnel through the territory of both states. To secure credit for the tunnel, the SOS joined with the
Jura–Bern–Luzern Railway to create the
Jura–Simplon Railway (French:
Compagnie du Jura–Simplon, SOS). The participation of the Swiss government led to the signing of a treaty with Italy on November 25, 1895 concerning the construction and operation of a railway through the Simplon from Brig to Domodossola by the Jura–Simplon Railway. The route of the tunnel was determined by military considerations, so that the state border between the two countries was in the middle of the tunnel, allowing either country to block the tunnel in the event of war. On 1 May 1903, the Jura-Simplon Railway was nationalized and integrated into the network of the
Swiss Federal Railways (SBB), which completed the construction of the tunnel.
Construction on 29 May 1905. The construction of the tunnel was carried out by the Hamburg engineering company Brandt & Brandau, of Karl Brandau and . On average, 3,000 people per day worked on the site. They were mostly Italians, who suffered under very poor working conditions: 67 workers were killed in accidents; many died later of diseases. During the work, there were strikes, which led to the intervention of vigilantes and the
Swiss army. With up to of rock over the tunnel, temperatures of up to were expected. Therefore, a new building method was developed. In addition to the single-line main tunnel, a parallel tunnel was built, with the tunnel centres separated by , through which pipes supplied fresh air to the builders in the main tunnel. It was envisaged that the parallel tunnel could be upgraded to a second running tunnel when required. The first Simplon Tunnel ( in length) was built almost straight, with only short curves at the two tunnel portals. On 24 February 1905, the two halves of the tunnel came together. They were out of alignment by only horizontally and vertically. Construction time was years, rather than years, due to problems such as water inflows and strikes. Silver Medallion by
Giannino Castiglioni for the
Milan International Exhibition 1906. The South Portal of the Simplon Tunnel is on the obverse.
Electrification and operation Operations commenced through the tunnel on 19 May 1906. Because of its length among other things, it has operated with
electric traction rather than
steam from the beginning. The official decision to use electricity was made only half a year before its opening by the then-still-new SBB.
Brown, Boveri & Cie (BBC) were commissioned to carry out the electrification. They decided in 1904 to use the
three-phase system being introduced in Italy, with a three-phase power supply of 3,400 volts at 15.8 Hz using two overhead wires with the track acting as the third conductor. BBC had no electric locomotives and initially acquired three locomotives built for the
Ferrovia della Valtellina—the owner of the lines from
Colico to
Chiavenna and
Tirano, which had been electrified with this system in 1901 and 1902—from their owner, the
Rete Adriatica (Adriatic Network) railway company. These three locomotives (which became
FS Class E.360) hauled all traffic through the tunnel until 1908. On 2 March 1930, the Simplon tunnel was converted to 15 kV, 16.7 Hz AC (single-phase).
Expansion Between 1912 and 1921, the second tube, known as Simplon II, was built. On 7 January 1922 the northern section from the northern portal to the passing loop in the middle of the tunnel was brought into operation, followed on 16 October 1922 by the southern section from the passing loop to the southern portal.
Second World War During the Second World War, on both sides of the border, there were preparations for the possible detonation of the tunnels. In Italy, the German army planned, as part of its 1945 withdrawal, to blow up the tunnel, but was thwarted by
Italian partisans with the help of two Swiss officials and Austrian deserters. == Present and future ==