Equipment manufacturing TBEA operates a manufacturing base in
Karjan, Gujarat,
India, under the name
TBEA Energy (India) Pvt Ltd., where it produces transformers, solar equipment, and cables for markets across India, Africa, and the Middle East.
Construction engineering TBEA has undertaken transmission and power infrastructure projects globally. • In
Ethiopia, the company was contracted to develop the transmission line from the
Gilgel Gibe III Dam to Addis Ababa in 2009. • In
Zambia, TBEA signed a US$334 million EPC contract in 2010 with
ZESCO to build 330 kV high-voltage transmission lines, supplying Eastern, Luapula, Northern, and Muchinga Provinces. The project broke ground in 2012. • In
The Gambia, TBEA constructed the 23 MW Jambur Solar Power Station, commissioned in March 2024. It was part of the Gambia Electricity Restoration and Modernization Project (GERMP) with funding from the World Bank, European Investment Bank, and EU.
Power stations In
Kyrgyzstan, TBEA was selected to reconstruct a power plant in Bishkek. The decision, reportedly influenced by political pressure, led to controversy over inflated costs and corruption allegations against local officials. The plant suffered a breakdown in 2018 shortly after reopening, but preliminary investigations indicated the failure occurred in a section not rebuilt by TBEA. ==Renewable energy==