On 4 May 1986 fuel pebbles became lodged in the fuel feeding system due to handling errors by the control room operator, specifically the manual override of the automated fuel loading mechanism, a deviation from standard operating procedures. Consequently, radioactive helium containing aerosols was released to the environment via the feed system's exhaust air chimney. The incident initially went unnoticed due to the overlap with radioactive fallout from the
Chernobyl disaster, complicating attribution. An anonymous informant from the THTR-300 workforce was the first to blow the whistle on the incident, and alleged that there was a deliberate attempt to conceal the radioactive emissions from authorities and environmental groups. The reactor operators had up to this point concealed the incident from regulatory authorities, then denied any irregularities, claiming that any emissions were within permissible limits and were part of normal operations. Official investigations were delayed, and environmental monitoring stations eventually identified unusual levels of radioactive Protactinium-233 (²³³Pa) isotopes, inconsistent with fallout from Chernobyl. The plant had to be ordered to shut down while the effects of the incident were assessed. Later analysis showed that the plant had released radioactive aerosols, estimated at up to
2 · 108 Bq, likely slightly below 180-day operation limits of 1,85 · 108 Bq, yet possibly above daily limits of 0,74 · 108 Bq. The
Nukem fuel factory in
Hanau was decommissioned in 1988 for security reasons, endangering the fuel fabrication chain. It was decided on 1 September 1989 to shut down THTR-300, which was submitted to the supervisory authority by the HKG on 26 September 1989 in accordance with the Atomic Energy Act. In the short operational life span of THTR-300 from 1985 to 1989, with only 423 full-load operating day equivalents, 80 incidents were logged. The nuclear power plant was plagued with shutdowns due to design issues, generating only 2891 GWh, far less than anticipated, never reaching the required availability of 70% (1988: 41%). == Decommissioning ==