Predecessor routes Early on, much of the route of the Trans-Canada Highway was first explored in order to construct the
Canadian Pacific Railway in the late 19th century, a route which much of the mainline TCH route later ended up following. The Trans-Canada Highway was not the first road across Canada. In British Columbia, the highway was predated by the
Crowsnest Highway, the
Big Bend Highway, and the
Cariboo Highway, all of which were constructed during the
Great Depression era. Many of the earlier highways in British Columbia were largely gravel and had many frequent inland ferry crossings at wide rivers and lakes. In Alberta, the section between Calgary and Banff was predated by the Morley Trail (now Highway 1A), which was driveable starting in the 1910s and paved in the 1930s. The first route over the Central Canadian Rockies to connect Calgary to British Columbia was the
Banff–Windermere Parkway, which was opened in 1922 and is now numbered as Highway 93. Sections of road across the Prairies have also existed since the 1920s. A gravel road connection across northern Ontario (Highway 17) was constructed starting in 1931. While this section was largely open by the late 1930s, it was not fully completed until 1951 (in large part due to
World War II interrupting construction). However, despite the gap, vehicles could still cross the country by getting ferried around the relatively short section of incomplete highway by either rail or water, and Highway 11 was completed to Hearst from the east by 1937 and Nipigon by 1943.
Opening The system was approved by the Trans-Canada Highway Act of 1949, with construction commencing in 1950. The highway officially opened in 1962, with the completion of the
Rogers Pass section of highway between
Golden and
Revelstoke. This section of highway bypassed the original Big Bend Highway, the last remaining section of gravel highway on the route. Upon its original completion, the Trans-Canada Highway was the longest uninterrupted highway in the world. Construction on other legs continued until 1971, when the last gap on Highway 16 was completed in the Upper
Fraser Valley east of
Prince George, at which point the highway network was considered complete.
Since completion (1960–2000) When the Trans-Canada Highway first opened, it was almost exclusively a two-lane route for its whole length across the country. While at the time it was considered a major improvement to the gravel roads and ferries it replaced, it was soon believed to be insufficient to handle the growing traffic volumes. In response, several provinces began to construct realignments, freeway widenings, and twin sections of highway in response to traffic flow and safety concerns. In British Columbia, the Upper Levels Freeway alignment was opened in 1960 through
Metro Vancouver with the completion of the
Second Narrows Crossing, which allowed the TCH to bypass downtown Vancouver's streets and the narrow
Lions Gate Bridge. The four-lane Upper Levels Freeway was constructed to a relatively low standard, with narrow lanes, low overpasses, and no proper merge ramps. It remains in this state in the present day. Between 1962 and 1964, Highway 1 was rerouted onto a new four-lane freeway bypass between
Vancouver and
Chilliwack. This section of highway was originally part of British Columbia's own
400 series of highways, until the designation was replaced by Highway 1. A freeway alignment on the Trans-Canada Highway between Chilliwack and
Hope opened in 1986. The opening of the
Cassiar Tunnel in 1990 bypassed the last sets of signal lights in Vancouver, rendering the whole alignment of the Trans-Canada Highway through the Lower Mainland a freeway. All bypassed sections of the highway were absorbed into various urban and rural road networks. The older freeways in the Lower Mainland were largely built as a parkway design, with wide, forested medians and low overpasses (a road configuration that was common across North America at the time). After the opening of the
Coquihalla Highway in 1986, the Trans-Canada Highway through the
Fraser Canyon received less traffic, because the freeway bypass shortened the drive between Hope and Kamloops by 90 minutes. However, the route was retained as part of the Trans-Canada Highway, and is considered a scenic route and a valuable part of the Fraser Country Circle Tour. The opening of the Coquihalla was also an economic disaster for many of the towns along the Fraser Canyon section of the Trans-Canada Highway, since most of the travel and tourism business along the route quickly dried up when most of the traffic took the new highway. The towns continue to be largely deprived of wealth, and some are close to being abandoned. On the other hand,
Merritt, located midway up the new Coquihalla highway, ended up booming, and continues to grow as a tourism and travel centre. The Coquihalla project also realigned Highway 1 (TCH) to a new freeway bypass around
Kamloops. Plans for a freeway to bypass or eliminate
traffic congestion and road hazards along the heavily travelled route from Victoria to Nanaimo on Vancouver Island were cancelled during the
recession that followed the
1987 stock market crash. In Alberta, between 1964 and 1972, the Trans-Canada Highway was completely rerouted from its former two-lane alignment along the
Bow River to a new, more direct, four-lane freeway between Banff and Calgary, resulting in the bypassing of several towns, such as
Canmore and
Cochrane. Prior to this change, one of the first
traffic circles in Canada existed on Highway 1 at the "gateway" junction for Banff from at least as early as the 1950s until about 1980 when it was replaced by an interchange. In the rest of Banff National Park, much of the predecessor Highway 1 parkway was bypassed by a new two-lane route in the 1960s. This new route was subsequently twinned in phases beginning in about 1980. The original route between Banff and
Lake Louise remains as the
Bow Valley Parkway and Lake Louise Drive, while a section over
Kicking Horse Pass was abandoned and is now only open to pedestrians and cyclists. Between 1973 and 1990, the highway was twinned from Calgary to the Saskatchewan Border. In 1970, plans were made for a six-to-eight-lane freeway to carry the Trans-Canada Highway though the heart of North Calgary, but the plan was soon dropped due to
citizen outcry. Between Ottawa and the Ontario–Quebec border, the Trans-Canada Highway designation was taken from the two-lane Highway 17 and applied to the existing Highway 417 freeway in 1997–98. On April 1, 1997, the
Ministry of Transportation of Ontario (MTO) transferred the responsibility of maintenance and upkeep along of Highway 17 east of "the split" with Highway 417 to Trim Road (Regional Road 57) to the
Regional Municipality of Ottawa-Carleton, a process commonly referred to as
downloading. The Regional Municipality then designated the road as
Regional Road 174. Despite the protests of the region that the route served a provincial purpose, a second round of transfers saw Highway 17 within Ottawa downloaded entirely on January 1, 1998, adding an additional to the length of Regional Road 174. The highway was also downloaded within the
United Counties of Prescott and Russell, where it was redesignated as County Road 17. The result of these transfers was the truncation of Highway 17 at the western end of Highway 417. 1990 saw the opening of the two-lane
Kenora Bypass, providing through traffic with a way to avoid the congested town. Starting in the 1960s, Quebec began to build its
Autoroute network. Many sections of Trans-Canada Highway were widened to freeway standards during that era of highway construction. Starting in 1987, New Brunswick began to widen its section of TCH to four lanes. Work to make the route a full freeway began in the late 1990s and was completed in 2007. The
Confederation Bridge connecting PEI to New Brunswick opened in 1997. Replacing the ferry that previously serviced that route, it was hailed as a major accomplishment.
Recent changes (2000–present) In 2000 and 2001,
Transport Canada considered funding an infrastructure project to have the full Trans-Canada system converted to limited-access divided highways. Although construction funding was made available to some provinces for portions of the system, the federal government ultimately decided to not pursue a comprehensive limited-access highway conversion. Opposition to funding the limited-access widening was due to low traffic levels on parts of the Trans-Canada Highway. Prior to the start of the
Great Recession in 2008, the highway underwent some changes through the
Rocky Mountains from
Banff National Park to
Golden, British Columbia. A major piece of this project was completed on August 30, 2007, with the
new Park Bridge and Ten Mile Hill sections opening up of new four-lane highway. Other smaller four-lane widening projects on the Trans-Canada Highway in the interior of British Columbia were also built around the same time. As part of the
Gateway Program, of congested four-lane Highway 1 freeway in Metro Vancouver were widened to an eight-lane buildout starting in 2012. This project continues into the present, with the current goal of rebuilding the freeway to a minimum six-lane layout from Langley to Abbotsford by 2025. The twinning of the highway in Alberta's
Banff National Park continued, with the final of Highway 1 between Lake Louise and the British Columbia border opened to traffic on June 12, 2014, making the whole length of Alberta's main Trans-Canada Highway route a minimum four lanes.
Stoney Trail began construction in 2005, and was usable as a bypass around Calgary when its northeastern section opened in 2010. Although not officially part of the Trans-Canada Highway system, Stoney Trail plays a critical role in providing through traffic on the Trans-Canada Highway with a way around the city. During the 2000s, much of the Trans-Canada Highway through Saskatchewan and Manitoba was twinned. In 2019, the
Regina Bypass opened, resulting in the Trans-Canada Highway being realigned around the city and bypassing a section of heavily signalized arterial road on
Victoria Avenue. The 2010s saw changes to other routes in the Trans-Canada Highway system as well.
Ontario Highway 400 began to be extended towards Sudbury, replacing
Highway 69 and resulting in a freeway alignment for part of the Southern Ontario Trans-Canada Highway Route. Work on this project is continuing, with almost of freeway currently under construction. Edmonton is currently attempting to widen its urban section of
Highway 16 to a six-lane freeway. Large amounts of Highway 16 in Alberta were twinned during the 2000s. Despite these many widenings, over half of the mainline Trans-Canada Highway still remains in its original two-lane state, and only about 15% of the mainline's length is composed of freeway comparable to that of the
Interstate Highway System. In 2012, a series of free public
electric vehicle charging stations were installed along the main route of the highway by a private company, Sun Country Highway, permitting electric vehicle travel across the entire length, as demonstrated by the company's president, Kent Rathwell, in a publicity trip from St. John's, NL, to Victoria, BC, in a
Tesla Roadster. , this made the TCH the longest electric-vehicle-ready highway in the world. == Future ==