The U2 Tower was a cancelled skyscraper which was proposed to be constructed in Dublin, Ireland. The site proposed was in the South Docklands (SODO) campshires, at the corner of Sir John Rogerson's Quay and Britain Quay, by the confluence of the River Liffey, the River Dodder, and the Grand Canal. The design announced on 12 October 2007 was by Foster + Partners. Reports suggested a building height of 120 metres, "well over 120 metres", and 180 metres, any of which would have made it the tallest building on the island of Ireland. The building was planned to be an apartment building, with a recording studio owned by the rock group U2 in a "pod" at the top. Construction was to begin in 2008 and end in 2011, at a cost of €200m. In October 2008, the project was cancelled because of the economic downturn at the time. Proposals to revive the plan were reported in July 2013. However, they did not come to fruition and the 79-metre, 22-storey Capital Dock development has since been built on the site.

History
The Dublin Docklands Development Authority (DDDA) was established in 1997 to regenerate the brownfield sites and underused warehouses in the Docklands at the mouth of the River Liffey in Dublin. In 2000, the DDDA proposed a landmark tower for the Britain Quay site. The involvement of U2 was part of a deal in 2001 when the DDDA had acquired by compulsory purchase the site of U2's previous studio on Hanover Quay. In October 2002, the DDDA announced an architectural design competition for the tower, initially to be 60 metres tall, which would house apartments and a penthouse recording studio for U2. The judging panel was not revealed till after the winner was announced. It included the president of the Royal Hibernian Academy, the chairman and two other members of the DDDA, Dublin's City Architect, and Adam Clayton of U2. The panel initially chose as the winner an entry which was later disqualified after legal advice because the DDDA had lost the details of which firm had submitted the design and so were unable to notify the winner. This was in conjunction with the also-cancelled construction of the 120-metre Watchtower in the Point Village complex on the north bank of the Liffey, opposite the U2 tower. The DDDA envisaged the two towers forming a "landmark entry" and "visual gatepost" for the city from Dublin Port. Minister for the Environment, Heritage and Local Government Dick Roche approved the DDDA's plans in July 2006. The DDDA applied for planning permission for the U2 tower on 14 September 2006. This application further increased the height of the tower to 130m. The provisions of Section 25 of the DDDA Act, 1997 were used to fast-track the application. It was approved on 2 October 2006. ==Problems==
Problems
Developers Dunloe Ewart (subsequently taken over by Liam Carroll) had secured planning permission in 2000 for a 100-metre building on a site next to that of the U2 tower. The DDDA objected to this in 2005 as it wanted the U2 tower to be an isolated landmark. Dublin City Council refused to extend planning permission on Carroll's undeveloped site after it expired. In September 2007, Carroll appealed this in the Commercial Court. Some residents of Ringsend accused the DDDA of "arrogance", claiming that extra revenue from two towers could fund social housing schemes in nearby areas. Others expressed discontent at the presence of a skyscraper in a historically low-rise area. Concerns were expressed about a possible conflict of interest for U2 in the building tender process, when it emerged that the band were joint backers of Geranger. After the original BCDH bid's success, it was pointed out that U2 manager Paul McGuinness is the brother-in-law of BCDH architect Felim Dunne. Construction tenders were able to submit price quotations for both the original BCDH design and an alternative of their own choosing. Delays at all stages of the design and planning phases were commented upon. The estimated cost and completion date later moved from €55m and early 2008 in September 2006 to €200m and late 2011 in October 2007. ==Design==
Design
The predicted price of a 2-bed apartment in the tower was estimated in October 2006 at €1–1.5 million. BCDH design The BCDH design had a 45-degree twist, Kennedy-Wilson proposal now stands at the U2 Tower's site It was reported in July 2013 that Kennedy-Wilson, an American firm, was planning to buy the site off NAMA and develop an 18-story U2 Tower, half the height of the earlier plan. This plan was later cancelled, being replaced by the 79-metre, 22-storey Capital Dock development which currently stands on the site. ==References==
tickerdossier.comtickerdossier.substack.com