The $1.1 billion project was split into four parts, each built by a different company, and supervised by an independent consortium. There were up to 3,300 workers simultaneously on the project, which took 18 months of preparation and 18 months of construction. The financing is via a build-operate-transfer system by Lusoponte, a private consortium that receives the first 40 years of tolls for both Lisbon bridges. Lusoponte's capital is 50.4% from Portuguese companies, 24.8% from French, and 24.8% from British. The bridge has a life expectancy of 120 years, having been designed to withstand wind speeds of and hold up to an earthquake 4.5 times greater than the standards of building resistance in Lisbon. The deepest foundation piles, up to in diameter, were driven down to under
mean sea level. Environmental pressure throughout the project resulted in the left-bank viaducts being extended inland to preserve the marshes underneath, as well as the lamp posts throughout the bridge being tilted inwards so as not to cast light on the river below. ==Toll==