First ideas to dig a canal to Tilburg Whatever the eventual form of the canal, the primary reason to dig it was to connect Tilburg to the Dutch system of inland waterways. By the end of the 18th century, Tilburg was the biggest town of the
Meierij van 's-Hertogenbosch, but all transport to and from Tilburg took place over unpaved roads. In 1863 the
Breda–Eindhoven railway connected Tilburg to Breda, and in 1865 to Eindhoven. At about that time the
textile industry of Tilburg was booming, and used an enormous amount of coal. In April 1869 J. van de Griendt proposed a canal from the Zuid-Willemsvaart to Tilburg. It was to start between locks 5 and 6 or 6 and 7, and to take its course along
Sint-Oedenrode,
Liempde,
Moergestel and
Oisterwijk to Tilburg. It could easily transport a lot of water for use by the emerging Tilburg industry. A facility would have to be made to discharge this water towards the Meuse. The plan took into account that making a canal from Tilburg to the
Oude Maasje (Meuse) was much more costly, because of the greater difference in height. However, this could be done at a later time. In July 1869 the provincial government allowed 1,500 guilders to investigate a plan for a canal from the Zuid-Willemsvaart over Tilburg to Dongen or
's Gravenmoer. This was a plan by the then chief engineer, but the investigation was to include Van de Griendt's plan. In 1873 a commission for construction of the Tilburg canal made a report. It could not make a specific plan, because the municipalities along the canal were not prepared to give enough funding. In 1876 the commission sent in a report for a small canal from the Zuid-Willemsvaart to Tilburg, which would cost 750,000 guilders. In July 1876 a decision was postponed, and in July 1877, the provincial government refused to contribute the 250,000 guilders needed as her contribution to the canal.
The Bake plan In 1876 the provincial Waterstaat of North Brabant began to operate. F.C. Bake from the
Staatsspoorwegen became its head and chief engineer. In April 1878 Bake and the municipalities of Breda, Tilburg and
Oosterhout were planning a canal from Eindhoven via Tilburg to the Amer. This was the first plan that resembled the current Wilhelmina Canal. In 1889 the need for canal was again discussed in the provincial government. The chief engineer of Waterstaat came up with a plan in June 1890. It had the same size as the Zuid-Willemsvaart, and would start there between locks 6 and 7. The description of the section east of Tilburg closely resembles the canal as it would later be built. There was also a variant in which the section between Tilburg and the Zuid-Willemsvaart would be narrower, i.e. only 6 m wide at the bottom of the canal. The plan for the locks foresaw a lock with a double set of gates near the Zuid-Willemsvaart, to this lock could also operate if the level of the Zuid-Willemsvaart was lower. Regular locks would lift 2.5 m. Two double (sequential) locks would lift 5 m. A significant change from the 1877 plan was that the canal would end at Oosterhout instead of at the Moerdijk. This had to do with the Amer becoming more navigable in the meantime. The plan was signed by engineer Schevichaven. A letter by chief engineer Bake was attached to the plan. The estimated cost for the plan was 4,512,000 guilders. The plan came to nothing, primarily because the national government did not want to execute it. The province thought it too risky to do it on her own, also because the maintenance would then also become a provincial task. The discussion centered on whether the canal was a local interest, or a national interest. In the senate Jacob van den Biesen noted that the government thought projects like the
Nieuwe Waterweg (25 million), the
North Sea Canal (12.5 million), and the
Nieuwe Merwede (20.5 million) to be of national interest, but that the result was that North Brabant had to pay for these, but got nothing in return, not even 2 million for the canal. Van den Biesen then suggested that he might take a principal stand, and vote against all other projects if Brabant got nothing. The name Wilhelmina Canal dates at least to April 1901. In 1903 Minister
Johannes Christiaan de Marez Oyens made some changes to the plan, leading to a significant increase in cost. On 9 February 1904 the provincial government of North Brabant voted to contribute 2.5 million guilders to construction of the canal by the national government. In November 1904 a law to construct the canal was sent to the House of Representatives, but it soon became clear that this law would only lead to actual construction of the canal if funding became available. The people of North-Brabant thought that they had been fooled by the minister. On 11 May 1905 the law for the canal was approved by the House of Representatives.
Construction starts In spite of the non-committal character of the law, the government started to delimit the future course of the canal in July 1906. Soon after, 500,000 guilders for the canal were added to the 1907 budget. By May 1907 a detailed map of the section in Tilburg was published. In these years a lot of time and money was spent on buying, and where necessary
compulsory purchase, of grounds for the canal. In November 1908 the
compulsory purchase law for the canal was treated in the House of Representatives. Overall construction was slow. In 1911 there was a budget of 750,000 guilders. Of this sum 600,000 was spent on purchasing land, and only 75,000 were spent on construction. It led to another heated debate in
The Hague.
West of Tilburg On 8 December 1909 construction of the first section of the canal was tendered. This stretched from the
Donge to the Koningsdijk in Oosterhout, and included dredging the Donge. The lowest bid was by H.G. den Hartog from The Hague for 258,900 guilders. In mid March 1910 the workers were constructing sheds. They would start digging in April. In October 1910 Den Hartog also got the order to construct a quay , just north of where the Mark Canal was. This is still in use. On 15 May 1912 the section from the Donge to the Koningsdijk and its quay was opened. The Mark Canal, which connected Breda to the Meuse, came next. In 1911 there was a 310,000 guilders budget for the Mark Canal from Oosterhout to the river
Mark. In October 1912 the (since replaced) lock at the eastern end of the Mark Canal, south of the Koningsdijk, was tendered. The government gave the lock at the Mark Canal the dimensions 65 * 15 m, with a passage width of 7.50 m. This was enough for two ships of 60 * 7 * 1.90 m and better than agreed upon with North-Brabant. In October 1913 construction of the Mark Canal itself was tendered for 734,400 guilders. On 4 October 1915 the Mark Canal was opened. Ships of 60 * 7 * 2.10 m were allowed on the canal. The section from Oosterhout to Dongen faced a particular challenge. It was dug upstream to a place without surface water. The water would therefore have to be pumped upstream. Construction of Lock I started in April 1914. Later in April 1914, construction of the section between Lock I and the Voldijk, about 5 km east of Dongen was tendered. On 12 March 1917 this section was opened till the quay of Dongen.
World War I would speed up the section from Dongen to Tilburg, because there was a lot of unemployment. In September 1914 the government therefore asked for an extra 500,000 to speed up the Wilhelmina Canal. Shortly after, the government asked 5 contractors to make a bid for digging a section east of the Voldijk by hand. It was rumored that the constructor of the almost complete Mark Canal got the order. On 2 December 1914 Lock II (near the Voldijk) and the double lock Lock III were tendered, together with digging a projected stretch of the canal in Tilburg municipality. The contract was won bij J.P. Broekhoven from Hengelo for 1,038,000 guilders. The tendered section of the canal was probably that which was between the two locks, or the section stretching to the road from Tilburg to Loon op Zand. In late June 1915 D. van der Zee was appointed as extraordinary overseer for construction of the section from Lock III till that road. On 14 February 1919 the section between Dongen and the Tilburg quay at the Lijnschestraat (now IJsselstraat), east of Lock III was opened. The projected end point of the canal in Tilburg was the (Pius Harbor) just south east of the city center. On 24 July 1918 construction of two sections was tendered. The first was that between the Tilburg-Loon op Zand road and the Nieuwe Leij, and included a side canal towards Tilburg proper. The other section stretched to
Haghorst. The side canal would lead to Tilburg's inland harbor Piushaven. The plan for a harbor, housing and industry near the Pius park and street was approved in April 1920. It seems that celebrations for the opening of the harbor were included in those for the 25th anniversary of
Queen Wilhelmina's reign in August 1923. These included a gondola tour from the Quay at Lijnsheike to Piushaven.
East of Tilburg Construction of the section east of Tilburg started in the east, at the
Zuid-Willemsvaart, because that is where the water was. On 29 April 1916 Lock V, just west of
Lieshout was tendered. On 25 October 1916 the canal section from the
Zuid-Willemsvaart till the Breugelsche Beek (just east of
Son) was tendered. In June 1917 the section from the Breugelsche Beek till the eastern border of the
municipality of Best was tendered. In October 1917, the connecting section from the eastern border of Best till the Heersdijk (just east of Oorschot) was tendered. In December 1917 the connecting section between the Heersdijk and the Beerse Heide (east of Haghorst) was tendered. On 24 July 1918 the section from the Emmerseweg in Haghorst (location of Lock IV) till Nieuwe Leij in Tilburg was tendered together with final section from the Meuse till Tilburg. On 9 January 1922 the section from Lieshout till the
Double-beam drawbridge in the Kwadeweg at the hamlet Stad van Gerwen was opened. On 22 May 1922 the section from this bridge till a like bridge south of Breugel was opened. On 4 April 1923 the last sections of the Wilhelmina Canal were opened. == The canal in 1925 ==