In February 1997, the bridge was closed to all traffic except buses, bicycles, motorcycles, emergency vehicles and pedestrians to allow further essential repair works. Structural elements of the bridge were corroded or worn, in particular cross girders and deck surfacing, as well as some areas of masonry. The bridge was declared a
Grade II* listed structure in 2008, providing protection to preserve its special character from unsympathetic development. The bridge was again temporarily closed to traffic to allow repairs in early 2014. Further repairs and strengthening works were delayed in November 2016 in a wrangle over funding between
Hammersmith and Fulham Council and
Transport for London (TfL). LBHF leader Steven Cowan said: "There's no way that this council is going to spend anything like that money, the majority of this issue is the responsibility of TfL and we will work with them to make sure the bridge is fit for public purpose".
2019: Closure With funding for a major refurbishment still not resolved, on 10 April 2019, Hammersmith and Fulham Council closed the bridge indefinitely to motor traffic on safety grounds. Pedestrians and cyclists were allowed to use the bridge. On 10 October 2019,
Planning in London magazine published the results of its competition for a quick fix to Hammersmith Bridge's closure. The winning entry, by marine civil engineers Beckett Rankine, consisted of a prefabricated temporary road and foot bridge downstream of Hammersmith bridge and connecting in to Queen Caroline Street on the Hammersmith side. Beckett Rankine claimed that the bridge's cost could be recouped by charging a toll on vehicles. On 13 August 2020, the structural issues worsened in a heatwave, and the bridge was closed to cyclists and pedestrians, completely shutting use of the bridge. The costs were reported as £141 million to fully repair the bridge and £46 million to stabilise it for use by cyclists and pedestrians. Neither the council nor the transportation authority had this money available. In November 2020, engineers proposed a temporary double-decked steel structure within the existing bridge to allow damaged elements to be removed for repair. The scheme, designed by
Foster and Partners with bridge engineers
COWI, was backed by the local council and presented to Shapps. The scheme, costed at around £100 million, would allow the bridge to reopen for pedestrians and cyclists in the summer of 2021, with cars and vans able to cross two months later, and full restoration by 2023. The proposals were discussed on 19 March 2021 at a government taskforce meeting, and plans for the work to be funded through a £3 toll scheme were accepted. In December 2020, reports suggested that the full closure was overly cautious, and that little work would be needed to reopen the bridge to pedestrians and cyclists.
2021: Partial reopening On 1 June 2021, TfL, Hammersmith and Fulham Council and central government came to a cost-sharing agreement that would reopen the bridge in the near future. The following month, council leader Stephen Cowan announced that the bridge would partially re-open to pedestrians and cyclists from 17 July 2021. For the first phase, a £6 million, 46-week stabilisation plan designed by consultants
Mott MacDonald was approved by the council in August 2021. A second phase, involving extensive strengthening and full restoration, was to allow the bridge to reopen to motor vehicles.
2022: Repairs File:Hammersmith Bridge footings repair works.jpg|Repair works to the bridge footings File:Hammersmith Bridge footing cooled in heatwave.jpg|Footing foil-wrapped and cooled in heatwave, with sensors In February 2022, highways contractor
FM Conway started work on a 10-month first phase of the restoration. The council approved the full £8.9 million cost, hoping that DfT and TfL would reimburse them for their one-third shares. Completion of this work was delayed a year as steel became hard to procure due to the
Russian invasion of Ukraine. In October 2022, Hammersmith and Fulham Council agreed to lodge a planning application to temporarily double-deck the bridge to speed up its restoration. The council intended to appoint a private sector contractor to design, renovate, finance and maintain the bridge, with the council's construction and ongoing operation and maintenance costs funded by tolls. while construction was paused to allow the repair of a steel gantry damaged in a collision with a boat, MV
Emerald of London, in December 2023. The last stage was to replace the
mechanical bearings on the four corner pedestals of the bridge, after which the council would "review e-mobility options to shuttle residents across the bridge, notably the elderly or disabled". In January 2024, the cost of repairing the bridge had increased to £250 million (US$316 million). A day later, London Mayor
Sadiq Khan said that "I do want that bridge fit for purpose for vehicles" but neither Hammersmith & Fulham Council nor TfL had the money to make it so. TfL's 2024 Business Plan did not include funding for the bridge.
2025: Roadway reopened to pedestrians and cyclists After work on the hangers that link the bridge deck to its suspension chains, the roadway was resurfaced. Its deck is of plywood boards, bolted to timber supports; worn boards and some of the timbers were replaced, at a cost of £2.9 million. The bridge reopened to pedestrians and cyclists in April 2025, with the roadway divided into wide pedestrian and cycle lanes. Pedestrians can also use the two outer footways. File:Hammersmith Bridge 2024 reopened as cycleway.jpg|February 2024: worn roadway reopened as cycleway File:Hammersmith Bridge 2025 roadway opened to pedestrians and cyclists.jpg|April 2025: resurfaced roadway opened to pedestrians and cyclists == Heraldry ==