Announcement In November 2011, the Scottish Government announced that it would upgrade the entire road between Perth and Inverness to a dual carriageway by 2025. The design contract was split into three lots with Lot 1 (Glengarry to Dalraddy) awarded to a
CH2M /
Fairhurst joint venture in April 2014. Lot 2 (Pass of Birnam to Glengarry) was awarded to
Jacobs in August 2014 and Lot 3 was awarded to an
Atkins /
Mouchel joint venture in December 2014. The contract for a preliminary section (outwith Lots 1 to 3) of the £3 billion project was awarded in June 2015. Preliminary work started in 2014 in preparation of main construction work. The first section was scheduled to open in the summer of 2017, but due to technical problems, this section suffered a slight delay and completed in September 2017 at a cost of £35 million. It is an isolated stretch of dual carriageway (i.e., this section is not an extension of an existing dual carriageway or something that fills the gap, as was done for the second and third section down below). Since Kincraig to Dalraddy was upgraded, a
2+1 road section (also known as WS2+1) was removed due to CD 109 requirements of the
Design Manual for Roads and Bridges (DMRB) requiring a minimum of a 2 km section of single carriageway between the dual carriageway and the WS2+1 section. and
Pass of Birnam, taken in 2021 The second section of the project was the 6-mile (10 km) section between
Luncarty and
Pass of Birnam, the first section of what was single carriageway north of Perth. After the £96 million contract was awarded to
Balfour Beatty in August 2018, construction works began in February 2019. Between September 2017 and February 2019 there were no works in relation with the dualling programme. This section was scheduled to finish in early 2021. Like the Kincraig to Dalraddy section, it experienced a slight delay meaning that this section was finished in August 2021 with off-carriageway works to finish by 2022. After the completion of the first two sections, 11 miles (18 km) of single carriageway had been converted to dual carriageway.
Proposed and under construction sections Between August 2021 and October 2024, no sections of the A9 were upgraded or under construction. The project will be delivered via a hybrid approach, utilising both '
design and build' (D&B) and 'mutual investment model' (MIM), a type of
public-private partnership, contracts. The third section to be upgraded is between
Tomatin and
Moy, also 6 miles long. This is the northernmost section of single carriageway for the scheme. In November 2023, Transport Minister
Fiona Hyslop announced three contractors had been shortlisted for this scheme: John Graham Construction Ltd, Sacyr UK Ltd and
Balfour Beatty Civil Engineering Ltd. Some preparation works to this section include trees being cut down and a new railway bridge on the
Highland Main Line, which were done in 2021 and 2022, ahead of the main construction work. The new railway bridge is also wide enough should the Highland Main Line be doubled in the future. It was initially projected that this section would be upgraded by the end of 2027. Delays due to Belfour Beatty needing to assess the "impact of weather and environmental restrictions around working in rivers and streams" have pushed the completion date to early 2028. Preparatory works on this section began in October 2024, and major construction started in May 2025. Initial ground survey and borehole samples took place for the section in 2020. In August 2024, three contractors were shortlisted for this scheme:
Balfour Beatty Civil Engineering Ltd, Wills Bros Civil Engineering Ltd and John Graham Construction Ltd. After the £152.7m contract was awarded to Wills Bros in July 2025, preliminary work started in November 2025, A prior information notice was published for the 4-mile (6.4 km) section between
Pitlochry and
Killiecrankie in May 2025, the fifth section of the project. It passes through nearby designated environmental sites including the
River Tay Special Area of Conservation. The contractor for this section will also upgrade existing
at-grade junctions at Pitlochry North and Pitlochry South and convert them both into
grade separated junctions. Four other sections of the project will be awarded contracts between 2028 and 2030. This was followed by
Crubenmore to
Kincraig a month later leaving the Pass of Birnam to Tay Crossing section as the last to start the statutory process. Draft orders were published on 30 May 2025, highlighting the start of the statutory process for this section. It will introduce two new grade-separated junctions and a new roundabout. When upgraded, it will bring many benefits to the surrounding areas. Unless stated otherwise, the source for the table is: ==Delays==