In early April 1943, an Allied agent reported "enormous trenches" being excavated at the Watten site, and on 16 May 1943 an RAF reconnaissance mission led to Allied photographic interpreters noticing unidentified activity there. Other large facilities were observed to be under construction elsewhere in the Pas-de-Calais. The purpose of the construction works was very unclear;
Lord Cherwell,
Winston Churchill's scientific adviser, admitted that he had little idea what "these very large structures similar to gun emplacements" were but he believed that "if it is worth the enemy's while to go to all the trouble of building them it would seem worth ours to destroy them." At the end of May, the British
Chiefs of Staff ordered that aerial attacks be carried out against the so-called "heavy sites" being built by the Germans. The British Chiefs of Staff noted that a daylight attack by US bombers was under consideration but they raised objections to the proposal, as the Air Staff thought that Watten had nothing to do with rockets, suggesting that instead it might be merely a "protected operations room". bomb to the roof on the south side of the bunker, photographed after the war in 1951 Only 35% of the Watten bunker had been completed by this time. It was clearly no longer possible to use it as a launch site, but the Germans still needed LOX production facilities to supply V-2 sites elsewhere. After surveying the site in September and October 1943, Organisation Todt engineers determined that the northern part of the facility was irretrievably damaged but decided to focus on completing the southern part to serve as a LOX factory. One of OT's engineers, Werner Flos, came up with an idea to protect the bunker from bombardment by building it up from the roof first. This was done by initially constructing a concrete plate, flat on the ground, which was thick and weighed 37,000 tons. It was incrementally raised by
hydraulic jacks and then supported by walls which were built underneath it as it was raised, becoming the roof. The resulting concrete cavern was intended to be used by the Germans as a bombproof liquid oxygen factory. The thickness of the roof was chosen on the assumption that Allied bombs were incapable of penetrating such a depth of concrete; the Germans, however, were unaware of the British development of
earthquake bombs. By the time of the D-Day landings, the foundations for five machines were finished and three were installed. On 1 July Dornberger ordered the removal of the machines. On 3 July 1944,
Oberkommando West gave permission to stop construction at both sites, which had been so disrupted by bombing that work could no longer proceed. Three days later an Allied raid succeeded in wrecking the interior of the Watten bunker with a
Tallboy bomb that brought down part of the roof. Finally, on 18 July 1944, Hitler decreed that plans for launching missiles from bunkers need no longer be pursued. Dornberger's staff subsequently decided to continue minor construction at Watten "for deception purposes". The site itself was now useless, as the Germans recognised when they wryly codenamed it
Concrete Lump. The Watten site was captured on 4 September 1944 by Canadian forces. The Germans had evacuated it a few days earlier and removed the pumps which kept the cavernous basement free from water; not long afterwards it began to flood. This made a substantial amount of the bunker inaccessible to the Allies.
Air raids ==Subsequent investigations and utilisation==